Assessment Year | 2015 |
---|---|
Principal Product | Machined Parts |
NAICS | 332721: Precision Turned Product Manufacturing |
SIC | 3451: Screw Machine Products |
Sales Range | $10 M to 50M |
# of Employees | 77 |
Plant Area |
60,000
ft2
|
Annual Production | 15,216,906
pieces
|
Production Hrs. Annual | 4,100
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $158,522 | 1,880,000 |
kWh
|
$0.084 |
Electricity Demand | $35,984 | 5,688 |
kW-mo/yr
|
$6.33 |
Natural Gas | $17,170 | 1,531 |
MMBtu
|
$11.21 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $106,332 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $68,499 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 3.4116: Meter recycled water (to reduce sewer charges) | $12,159 | $700 | - | - | - |
$12,159
-
Tgal
|
- | |
02 | 2.3134: Shift from daytime to nighttime operation | $1,098 | - | - |
$1,098
-
kW-mo/yr
|
- | - | - | |
03 | 2.7231: Use radiant heater for spot heating | $4,208 | $1,050 | - | - |
$4,208
-
MMBtu
|
- | - | |
04 | 2.4151: Develop a repair/replace policy | $58,864 | $75,499 |
$43,856
536,594
kWh
|
$15,008
-
kW-mo/yr
|
- | - | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,325 | - |
$3,967
48,543
kWh
|
$1,358
-
kW-mo/yr
|
- | - | - | |
06 | 2.4113: Install motor voltage controller on lightly loaded motors | $11,416 | $23,545 |
$9,339
114,263
kWh
|
$2,077
-
kW-mo/yr
|
- | - | - | |
07 | 2.4226: Use / purchase optimum sized compressor | $8,952 | $45,000 |
$7,323
89,600
kWh
|
$1,629
-
kW-mo/yr
|
- | - | - | |
08 | 2.2437: Recover waste heat from equipment | $3,773 | $4,785 |
$(-318.0)
(-3,885)
kWh
|
$(-71.0)
-
kW-mo/yr
|
$4,162
-
MMBtu
|
- | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $537 | $1,000 |
$1,912
23,389
kWh
|
$425
-
kW-mo/yr
|
- | - | $(-1,800.0) | |
TOTAL RECOMMENDED | $106,332 | $151,579 |
$66,079
808,504
kWh
|
$21,524
-
kW-mo/yr
|
$8,370
-
MMBtu
|
$12,159
-
Tgal
|
$(-1,800.0) | ||
TOTAL IMPLEMENTED | $68,499 | $81,284 |
$49,417
604,641
kWh
|
$16,720
-
kW-mo/yr
|
$4,162
-
MMBtu
|
- | $(-1,800.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs