Assessment Year | 2013 |
---|---|
Principal Product | Metal Stamping products |
NAICS | 336370: Motor Vehicle Metal Stamping |
SIC | 3465: Automotive Stampings |
Sales Range | $10 M to 50M |
# of Employees | 58 |
Plant Area |
63,000
ft2
|
Annual Production | 14,000,000
pieces
|
Production Hrs. Annual | 4,940
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $119,778 | 1,954,289 |
kWh
|
$0.061 |
Electricity Demand | $8,235 | 4,476 |
kW-mo/yr
|
$1.84 |
Electricity Fees | $28,215 | - |
|
- |
Natural Gas | $17,831 | 1,822 |
MMBtu
|
$9.79 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $19,018 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,754 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,100 | - |
$1,100
17,947
kWh
|
- | - | - | |
02 | 2.4151: Develop a repair/replace policy | $654 | $460 |
$623
10,164
kWh
|
$31
-
kW-mo/yr
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,448 | $1,000 |
$1,666
27,188
kWh
|
$82
-
kW-mo/yr
|
- | $(-300.0) | |
04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $3,551 | $3,500 | - | - |
$3,551
-
MMBtu
|
- | |
05 | 2.7224: Reduce space conditioning during non-working hours | $1,355 | $2,000 | - | - |
$1,355
-
MMBtu
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,219 | $7,254 |
$4,737
77,285
kWh
|
$202
-
kW-mo/yr
|
- | $280 | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,401 | $9,000 |
$4,066
66,344
kWh
|
$199
-
kW-mo/yr
|
- | $136 | |
08 | 2.7135: Install occupancy sensors | $1,290 | $1,400 |
$1,254
20,465
kWh
|
- | - | $36 | |
TOTAL RECOMMENDED | $19,018 | $24,614 |
$13,446
219,393
kWh
|
$514
-
kW-mo/yr
|
$4,906
-
MMBtu
|
$152 | ||
TOTAL IMPLEMENTED | $1,754 | $460 |
$1,723
28,111
kWh
|
$31
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs