ITAC Assessment: DL0230
ITAC logo
ITAC Assessment: DL0230
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Waffles
NAICS 311230: Breakfast Cereal Manufacturing
SIC 2043: Cereal Breakfast Foods
Sales Range $10
M
to 50
M
# of Employees 55
Plant Area 101,000
ft2
Annual Production 150,000,000
units
Production Hrs. Annual 8,760
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $872,813 8,619,910
kWh
Electricity Demand $230,164 22,499
kW-mo/yr
Electricity Fees $13,286 -
Natural Gas $604,280 43,983
MMBtu
TOTAL YEARLY COSTS $1,720,543
RECOMMENDED SAVINGS* $192,376 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4224: Upgrade controls on compressors $13,779 $15,504 $13,779
107,650
kWh
-
02 2.7273: Install desiccant humidity control system $44,058 $22,437 $38,933
304,162
kWh
$5,125
-
MMBtu
03 2.4224: Upgrade controls on compressors $100,915 $74,000 $100,915
788,400
kWh
-
04 2.2437: Recover waste heat from equipment $3,146 $2,040 - $3,146
-
MMBtu
05 2.6231: Utilize controls to operate equipment only when needed $11,418 - $11,418
89,203
kWh
-
06 2.2444: Use hot process fluids to preheat incoming process fluids $15,141 $10,000 - $15,141
-
MMBtu
07 2.6231: Utilize controls to operate equipment only when needed $3,919 $2,200 $3,919
30,616
kWh
-
TOTAL RECOMMENDED $192,376 $126,181 $168,964
1,320,031
kWh
$23,412
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs