Assessment Year | 2011 |
---|---|
Principal Product | High Speed Inkjet Printing Systems |
NAICS | 333244: Printing Machinery and Equipment Manufacturing |
SIC | 3555: Printing Trades Machinery and Equipment |
Sales Range | $100 M to 500M |
# of Employees | 640 |
Plant Area |
318,000
ft2
|
Annual Production | 10,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,302,498 | 19,199,683 |
kWh
|
$0.068 |
Electricity Demand | $159,897 | 2,784 |
kW-mo/yr
|
$57.43 |
Natural Gas | $560,341 | 49,507 |
MMBtu
|
$11.32 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $256,753 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $52,296 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $2,272 | $300 |
$2,127
32,019
kWh
|
- | - | - | - | $145 | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,467 | $25 |
$3,911
58,895
kWh
|
$556
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.4224: Upgrade controls on compressors | $24,064 | $1,075 |
$21,929
330,252
kWh
|
$2,135
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,026 | $500 |
$5,150
77,554
kWh
|
$501
-
kW-mo/yr
|
- | - | - | $(-625.0) | - | |
05 | 2.4321: Upgrade obsolete equipment | $3,710 | $12,661 |
$3,381
50,923
kWh
|
$329
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $3,343 | $500 |
$3,046
45,880
kWh
|
$297
-
kW-mo/yr
|
- | - | - | - | - | |
07 | 3.4116: Meter recycled water (to reduce sewer charges) | $11,144 | $600 | - | - | - | - |
$11,144
-
Tgal
|
- | - | |
08 | 3.4116: Meter recycled water (to reduce sewer charges) | $7,523 | $10,500 |
$7,523
9,859
kWh
|
- | - | - | - | - | - | |
09 | 2.6242: Minimize operation of equipment maintained in standby condition | $5,553 | $100 |
$4,303
64,800
kWh
|
- | - | - | - | - | $1,250 | |
10 | 2.6218: Turn off equipment when not in use | $844 | $50 | - | - | - |
$844
-
MMBtu
|
- | - | - | |
11 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $83,814 | $10,000 |
$15,684
236,206
kWh
|
- | - |
$68,130
-
MMBtu
|
- | - | - | |
12 | 2.7264: Interlock heating and air conditioning systems to prevent simultaneous operation | $37,935 | $100 |
$595
91,980
kWh
|
$6,108
-
kW-mo/yr
|
- |
$31,232
-
MMBtu
|
- | - | - | |
13 | 2.7221: Lower temperature during the winter season and vice-versa | $21,754 | $100 | - | - | - |
$21,754
-
MMBtu
|
- | - | - | |
14 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $17,701 | $20,000 |
$16,130
242,924
kWh
|
$1,571
-
kW-mo/yr
|
- | - | - | - | - | |
15 | 2.7224: Reduce space conditioning during non-working hours | $3,435 | $100 | - | - | - |
$3,435
-
MMBtu
|
- | - | - | |
16 | 2.7231: Use radiant heater for spot heating | $1,061 | $2,800 | - | - | - |
$1,061
-
MMBtu
|
- | - | - | |
17 | 2.9114: Use solar heat to make electricty | $23,107 | $145,390 |
$3,999
60,230
kWh
|
- | $19,108 | - | - | - | - | |
TOTAL RECOMMENDED | $256,753 | $204,801 |
$87,778
1,301,522
kWh
|
$11,497
-
kW-mo/yr
|
$19,108 |
$126,456
-
MMBtu
|
$11,144
-
Tgal
|
$(-480.0) | $1,250 | ||
TOTAL IMPLEMENTED | $52,296 | $1,075 |
$9,679
228,774
kWh
|
$6,961
-
kW-mo/yr
|
- |
$35,511
-
MMBtu
|
- | $145 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs