Assessment Year | 2009 |
---|---|
Principal Product | Hardwood Veneer |
NAICS | 321211: Hardwood Veneer and Plywood Manufacturing |
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 230 |
Plant Area |
84,400
ft2
|
Annual Production | 5,235,099
units
|
Production Hrs. Annual | 3,760
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $449,156 | 7,862,000 |
kWh
|
$0.057 |
Natural Gas | $18,073 | 1,765 |
MMBtu
|
$10.24 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $160,294 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,680 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.5194: Redesign process | $60,982 | $300,000 | - | - | - |
$10,982
-
MMBtu
|
- | $50,000 | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $46,758 | - | - |
$46,758
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.3511: Use plant owned transformers or lease transformers | $20,779 | $50,000 | - | - | $20,779 | - | - | - | |
04 | 2.4224: Upgrade controls on compressors | $9,841 | $10,000 |
$5,720
142,128
kWh
|
$4,121
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.6231: Utilize controls to operate equipment only when needed | $7,981 | $19,425 |
$7,981
275,232
kWh
|
- | - | - | - | - | |
06 | 2.8114: Change rate schedules or other changes in utility service | $6,273 | $1,000 | - | - | - | - |
$6,273
-
Tgal
|
- | |
07 | 2.4224: Upgrade controls on compressors | $3,255 | - |
$1,363
47,000
kWh
|
$1,892
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,202 | - |
$1,341
46,248
kWh
|
$1,861
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,223 | $1,000 |
$512
17,672
kWh
|
$711
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $160,294 | $381,425 |
$16,917
528,280
kWh
|
$55,343
-
kW-mo/yr
|
$20,779 |
$10,982
-
MMBtu
|
$6,273
-
Tgal
|
$50,000 | ||
TOTAL IMPLEMENTED | $7,680 | $1,000 |
$3,216
110,920
kWh
|
$4,464
-
kW-mo/yr
|
- | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs