Assessment Year | 2006 |
---|---|
Principal Product | Farm Machinery |
NAICS | 333111: Farm Machinery and Equipment Manufacturing |
SIC | 3523: Farm Machinery and Equipment |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
320,000
ft2
|
Annual Production | 12,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $191,750 | 4,844,200 |
kWh
|
$0.040 |
Electricity Demand | $49,035 | 13,692 |
kW-mo/yr
|
$3.58 |
Natural Gas | $471,507 | 43,244 |
MMBtu
|
$10.90 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $164,122 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $49,602 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1122: Re-size charging openings or add a movable door on equipment | $65,250 | $10,000 | - | - |
$65,250
-
MMBtu
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $43,883 | $133,640 |
$36,888
696,000
kWh
|
$4,990
-
kW-mo/yr
|
- | $2,005 | |
03 | 2.7261: Install timers and/or thermostats | $18,067 | $110 | - | - |
$18,067
-
MMBtu
|
- | |
04 | 2.7442: Keep doors and windows shut when not on use | $16,240 | - | - | - |
$16,240
-
MMBtu
|
- | |
05 | 2.1113: Reduce combustion air flow to optimum | $9,135 | $2,800 | - | - |
$9,135
-
MMBtu
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,387 | $3,150 |
$4,528
85,428
kWh
|
$612
-
kW-mo/yr
|
- | $247 | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,802 | $840 |
$3,201
60,390
kWh
|
$601
-
kW-mo/yr
|
- | - | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,097 | - |
$828
15,625
kWh
|
$269
-
kW-mo/yr
|
- | - | |
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,261 | - |
$1,059
19,975
kWh
|
$202
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $164,122 | $150,540 |
$46,504
877,418
kWh
|
$6,674
-
kW-mo/yr
|
$108,692
-
MMBtu
|
$2,252 | ||
TOTAL IMPLEMENTED | $49,602 | $3,750 |
$5,088
95,990
kWh
|
$1,072
-
kW-mo/yr
|
$43,442
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs