ITAC Assessment: GT0115
ITAC logo
ITAC Assessment: GT0115
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1982
Principal Product FABRICATED WINDOWS,DOORS
NAICS
n/a
SIC 2431: Millwork
Sales Range $5
M
to 10
M
# of Employees 80
Plant Area
n/a
Annual Production 66,400
pieces
Production Hrs. Annual 2,080
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $22,912 405,920
kWh
Natural Gas $5,863 1,540
MMBtu
Fuel Oil #2 $69,491 8,036
MMBtu
Other Energy $22,747 2,628
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,189 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,119 $2,000 $1,119
19,930
kWh
-
02 2.7261: Install timers and/or thermostats $2,512 $273 $343
6,155
kWh
$2,169
-
MMBtu
03 2.7492: Use proper thickness of insulation on building envelope $558 $1,440 - $558
-
MMBtu
TOTAL RECOMMENDED $4,189 $3,713 $1,462
26,085
kWh
$2,727
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs