ITAC Assessment: UD0690
ITAC logo
ITAC Assessment: UD0690
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Punches and dies
NAICS 336390: Other Motor Vehicle Parts Manufacturing
SIC 3569: General Industrial Machinery and Equipment, Not Elsewhere
Sales Range $5
M
to 10
M
# of Employees 70
Plant Area 55,000
ft2
Annual Production 143,000
pieces
Production Hrs. Annual 5,720
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $83,712 87,776
kWh
Electricity Demand $87,776 6,684
kW-mo/yr
Natural Gas $29,754 3,956
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $52,676 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,109

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
01 2.7242: Change zone reheat coils to variable air volume boxes $24,929 $9,930 $11,536
427,241
kWh
- $13,393
-
MMBtu
- -
02 2.7241: Install outside air damper / economizer on hvac unit $9,916 $9,244 $9,916
367,259
kWh
- - - -
03 2.7264: Interlock heating and air conditioning systems to prevent simultaneous operation $4,576 $7,366 $1,026
38,016
kWh
$700
-
kW-mo/yr
$2,850
-
MMBtu
- -
04 2.5123: Reduce fluid flow rates $4,171 $2,400 $2,039
75,504
kWh
$2,132
-
kW-mo/yr
- - -
05 2.2414: Use waste heat from hot flue gases to preheat $1,955 $5,625 - - $1,955
-
MMBtu
- -
06 2.4231: Reduce the pressure of compressed air to the minimum required $1,580 - $630
23,400
kWh
$950
-
kW-mo/yr
- - -
07 2.6218: Turn off equipment when not in use $1,533 $2,240 $1,533
56,784
kWh
- - - -
08 2.7124: Make a practice of turning off lights when not needed $1,197 $86 $338
12,519
kWh
$859
-
kW-mo/yr
- - -
09 2.7124: Make a practice of turning off lights when not needed $1,085 $6 $534
19,719
kWh
$551
-
kW-mo/yr
- - -
10 2.4155: Standardize motor inventory $952 $340 - - - $952
-
Tgal
-
11 2.8118: Check for accuracy of utility / power meters $352 - - - - - $352
12 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $430 $170 $150
5,720
kWh
$280
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $52,676 $37,407 $27,702
1,026,162
kWh
$5,472
-
kW-mo/yr
$18,198
-
MMBtu
$952
-
Tgal
$352
TOTAL IMPLEMENTED $11,109 $9,936 $3,845
142,640
kWh
$4,062
-
kW-mo/yr
$2,850
-
MMBtu
- $352
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs