ITAC Assessment: UD0684
ITAC logo
ITAC Assessment: UD0684
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product injection molded automotive parts
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 40,000
ft2
Annual Production 30,000,000
pieces
Production Hrs. Annual 5,760
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $318,127 6,440,628
kWh
Electricity Demand $64,853 15,552
kW-mo/yr
Natural Gas $253 22
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $121,447 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $34,560

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Fuel Oil #1 Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings
01 4.625: Develop standard operating procedures $34,560 - - - - - - $34,560 -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $23,504 $37,800 $19,763
420,480
kWh
$3,741
-
kW-mo/yr
- - - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $9,995 $29,250 $5,875
195,840
kWh
$3,823
-
kW-mo/yr
- - - $(-228.0) $525
04 2.3212: Optimize plant power factor $15,725 $6,450 $6,840
228,000
kWh
- $8,885 - - - -
05 2.4221: Install compressor air intakes in coolest locations $8,700 $770 $7,315
155,520
kWh
$1,385
-
kW-mo/yr
- - - - -
06 2.2614: Use cooling tower or economizer to replace chiller cooling $4,792 $100 $4,245
90,317
kWh
$547
-
kW-mo/yr
- - - - -
07 2.7221: Lower temperature during the winter season and vice-versa $4,780 - $4,780
101,694
kWh
- - - - - -
08 2.4225: Install common header on compressors $3,865 - $3,250
69,120
kWh
$615
-
kW-mo/yr
- - - - -
09 2.2511: Insulate bare equipment $3,252 $8,000 $2,734
58,176
kWh
$518
-
kW-mo/yr
- - - - -
10 2.7111: Reduce illumination to minimum necessary levels $2,396 $613 $1,474
47,232
kWh
$922
-
kW-mo/yr
- - - - -
11 3.4155: Meter waste water $1,513 $2,000 - - - - $1,513
-
Tgal
- -
12 3.5112: Reprocess spent oils on site for re-use $3,323 $3,503 - - - $3,323
-
MMBtu
- - -
13 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,290 $660 $1,085
23,040
kWh
$205
-
kW-mo/yr
- - - - -
14 2.7261: Install timers and/or thermostats $1,207 $4,000 $1,207
25,691
kWh
- - - - - -
15 2.4221: Install compressor air intakes in coolest locations $1,000 $1,400 $840
17,850
kWh
$160
-
kW-mo/yr
- - - - -
16 2.4231: Reduce the pressure of compressed air to the minimum required $965 - $810
17,280
kWh
$155
-
kW-mo/yr
- - - - -
17 2.4239: Eliminate or reduce compressed air usage $580 $110 $450
9,600
kWh
$130
-
kW-mo/yr
- - - - -
TOTAL RECOMMENDED $121,447 $94,656 $60,668
1,459,840
kWh
$12,201
-
kW-mo/yr
$8,885 $3,323
-
MMBtu
$1,513
-
Tgal
$34,332 $525
TOTAL IMPLEMENTED $34,560 - - - - - - $34,560 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Fuel Oil #1 Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs