ITAC Assessment: UU0028
ITAC logo
ITAC Assessment: UU0028
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Structural Steel, Pressure Vessels, and Plating
NAICS
n/a
SIC 3441: Fabricated Structural Metal
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 650,000
ft2
Annual Production 0
units
Production Hrs. Annual 8,760
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $21,672 812,760
kWh
Electricity Demand $34,283 337
kW-mo/yr
Electricity Fees $7,848 -
Natural Gas $175,321 30,540
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $208,339 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $42,770

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Primary Product Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $986 - - $986
-
kW-mo/yr
- -
02 2.3212: Optimize plant power factor $5,590 $9,800 - $5,590
-
kW-mo/yr
- -
03 2.7243: Improve air circulation with destratification fans / other methods $30,500 $7,600 - - $30,500
-
MMBtu
-
04 2.2437: Recover waste heat from equipment $1,450 $700 - - $1,450
-
MMBtu
-
05 2.4221: Install compressor air intakes in coolest locations $844 $406 $497
16,501
kWh
$347
-
kW-mo/yr
- -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,400 $2,000 $2,000
64,900
kWh
$1,400
-
kW-mo/yr
- -
07 2.7145: Install skylights $17,689 $2,800 $14,633
485,580
kWh
$3,056
-
kW-mo/yr
- -
08 4.132: Purchase new equipment to reduce material use / cost $147,880 $100,000 - - - $147,880
TOTAL RECOMMENDED $208,339 $123,306 $17,130
566,981
kWh
$11,379
-
kW-mo/yr
$31,950
-
MMBtu
$147,880
TOTAL IMPLEMENTED $42,770 $20,506 $2,497
81,401
kWh
$8,323
-
kW-mo/yr
$31,950
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs