Assessment Year | 2015 |
---|---|
Principal Product | Fire Hydrants |
NAICS | 331511: Iron Foundries |
SIC | 3321: Gray and Ductile Iron Foundries |
Sales Range | $100 M to 500M |
# of Employees | 488 |
Plant Area |
440,481
ft2
|
Annual Production | 114,195
pieces
|
Production Hrs. Annual | 8,170
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,694,362 | 54,144,239 |
kWh
|
$0.050 |
Electricity Demand | $1,275,442 | 140,096 |
kW-mo/yr
|
$9.10 |
Electricity Fees | $191,824 | - |
|
- |
Natural Gas | $445,843 | 74,874 |
MMBtu
|
$5.95 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $769,204 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $63,377 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1122: Re-size charging openings or add a movable door on equipment | $399,011 | $500,000 |
$399,811
8,034,794
kWh
|
- | $(-800.0) | - | |
02 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $193,249 | $400,000 |
$285,372
5,734,960
kWh
|
- | $(-571.0) |
$(-91,552.0)
-
MMBtu
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $26,435 | $41,578 |
$19,827
398,447
kWh
|
$6,661
-
kW-mo/yr
|
$(-53.0) | - | |
04 | 2.5122: Replace high resistance ducts, pipes, and fittings | $51,808 | $3,396 |
$51,912
1,043,258
kWh
|
- | $(-104.0) | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $7,614 | $2,218 |
$7,629
153,316
kWh
|
- | $(-15.0) | - | |
06 | 2.4226: Use / purchase optimum sized compressor | $37,056 | $105,000 |
$28,667
576,110
kWh
|
$8,463
-
kW-mo/yr
|
$(-74.0) | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $36,942 | $3,180 |
$23,876
479,824
kWh
|
$13,140
-
kW-mo/yr
|
$(-74.0) | - | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $17,089 | $500 |
$11,477
230,649
kWh
|
$5,646
-
kW-mo/yr
|
$(-34.0) | - | |
TOTAL RECOMMENDED | $769,204 | $1,055,872 |
$828,571
16,651,358
kWh
|
$33,910
-
kW-mo/yr
|
$(-1,725.0) |
$(-91,552.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $63,377 | $44,758 |
$43,703
878,271
kWh
|
$19,801
-
kW-mo/yr
|
$(-127.0) | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs