| Assessment Year | 2001 |
|---|---|
| Principal Product | Corrugated polyethylene tubing |
| NAICS |
n/a
|
| SIC | 3084: Plastics Pipe |
| Sales Range | $10 M to 50M |
| # of Employees | 45 |
| Plant Area |
22,500
ft2
|
| Annual Production | 12,000,000
lb
|
| Production Hrs. Annual | 6,600
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $127,226 | 4,543,800 |
kWh
|
$0.028 |
| Electricity Demand | $151,554 | 9,888 |
kW-mo/yr
|
$15.33 |
| Natural Gas | $2,307 | 372 |
MMBtu
|
$6.20 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $14,528 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,927 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $7,175 | $1,720 |
$3,770
134,640
kWh
|
$3,405
-
kW-mo/yr
|
- | |
| 02 | 2.6231: Utilize controls to operate equipment only when needed | $2,762 | $400 |
$1,109
39,600
kWh
|
$1,653
-
kW-mo/yr
|
- | |
| 03 | 2.2437: Recover waste heat from equipment | $1,426 | $700 | - | - |
$1,426
-
MMBtu
|
|
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,372 | - |
$721
25,740
kWh
|
$651
-
kW-mo/yr
|
- | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,089 | $132 |
$588
21,000
kWh
|
$501
-
kW-mo/yr
|
- | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $704 | $600 |
$370
13,200
kWh
|
$334
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $14,528 | $3,552 |
$6,558
234,180
kWh
|
$6,544
-
kW-mo/yr
|
$1,426
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $5,927 | $1,132 |
$2,788
99,540
kWh
|
$3,139
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs