ITAC Assessment: UD0634
ITAC logo
ITAC Assessment: UD0634
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Corrugated polyethylene tubing
NAICS
n/a
SIC 3084: Plastics Pipe
Sales Range $10
M
to 50
M
# of Employees 45
Plant Area 22,500
ft2
Annual Production 12,000,000
lb
Production Hrs. Annual 6,600
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $127,226 4,543,800
kWh
Electricity Demand $151,554 9,888
kW-mo/yr
Natural Gas $2,307 372
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $14,528 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,927

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.2511: Insulate bare equipment $7,175 $1,720 $3,770
134,640
kWh
$3,405
-
kW-mo/yr
-
02 2.6231: Utilize controls to operate equipment only when needed $2,762 $400 $1,109
39,600
kWh
$1,653
-
kW-mo/yr
-
03 2.2437: Recover waste heat from equipment $1,426 $700 - - $1,426
-
MMBtu
04 2.4231: Reduce the pressure of compressed air to the minimum required $1,372 - $721
25,740
kWh
$651
-
kW-mo/yr
-
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,089 $132 $588
21,000
kWh
$501
-
kW-mo/yr
-
06 2.4221: Install compressor air intakes in coolest locations $704 $600 $370
13,200
kWh
$334
-
kW-mo/yr
-
TOTAL RECOMMENDED $14,528 $3,552 $6,558
234,180
kWh
$6,544
-
kW-mo/yr
$1,426
-
MMBtu
TOTAL IMPLEMENTED $5,927 $1,132 $2,788
99,540
kWh
$3,139
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs