Assessment Year | 1996 |
---|---|
Principal Product | Pharmaceutical rubber items |
NAICS |
n/a
|
SIC | 3060: |
Sales Range | $10 M to 50M |
# of Employees | 300 |
Plant Area |
140,406
ft2
|
Annual Production | 14,000,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $476,087 | 12,665,592 |
kWh
|
$0.038 |
Electricity Demand | $387,453 | 26,783 |
kW-mo/yr
|
$14.47 |
Natural Gas | $158,893 | 42,777 |
MMBtu
|
$3.71 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $99,232 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $65,401 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $20,895 | $10,000 |
$8,321
221,278
kWh
|
$12,574
-
kW-mo/yr
|
- | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,441 | $3,000 |
$1,441
38,394
kWh
|
- | - | - | |
03 | 2.4239: Eliminate or reduce compressed air usage | $9,833 | $400 |
$3,835
101,993
kWh
|
$5,998
-
kW-mo/yr
|
- | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $1,498 | $1,700 |
$602
16,120
kWh
|
$896
-
kW-mo/yr
|
- | - | |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,744 | $600 | - | - |
$1,744
-
MMBtu
|
- | |
06 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $6,221 | $5,100 |
$3,046
80,891
kWh
|
$3,175
-
kW-mo/yr
|
- | - | |
07 | 2.7111: Reduce illumination to minimum necessary levels | $2,284 | $640 |
$553
14,654
kWh
|
$1,731
-
kW-mo/yr
|
- | - | |
08 | 2.4133: Use most efficient type of electric motors | $3,827 | $2,970 |
$1,874
49,824
kWh
|
$1,953
-
kW-mo/yr
|
- | - | |
09 | 2.2511: Insulate bare equipment | $932 | $549 | - |
$510
-
kW-mo/yr
|
$422
-
MMBtu
|
- | |
10 | 2.7425: Clean or color roof to reduce solar load | $3,582 | $4,720 |
$1,425
37,808
kWh
|
$2,157
-
kW-mo/yr
|
- | - | |
11 | 2.3191: Use demand controller or load shedder | $1,960 | $2,000 | - |
$1,960
-
kW-mo/yr
|
- | - | |
12 | 2.2612: Use cooling tower water instead of refrigeration | $25,015 | $18,000 |
$25,015
655,334
kWh
|
- | - | - | |
13 | 3.1191: Change procedures / equipment / operating conditions | $20,000 | $2,000 | - | - | - |
$20,000
-
lb
|
|
TOTAL RECOMMENDED | $99,232 | $51,679 |
$46,112
1,216,296
kWh
|
$30,954
-
kW-mo/yr
|
$2,166
-
MMBtu
|
$20,000
-
lb
|
||
TOTAL IMPLEMENTED | $65,401 | $38,619 |
$41,088
1,082,943
kWh
|
$23,891
-
kW-mo/yr
|
$422
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs