Assessment Year | 2015 |
---|---|
Principal Product | Steel Fabrication |
NAICS | 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing |
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 214 |
Plant Area |
600,000
ft2
|
Annual Production | 144,053
units
|
Production Hrs. Annual | 5,005
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $375,762 | 5,825,766 |
kWh
|
$0.065 |
Electricity Demand | $173,728 | 19,848 |
kW-mo/yr
|
$8.75 |
Natural Gas | $147,395 | 31,747 |
MMBtu
|
$4.64 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $107,735 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,047 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,206 | $1,000 |
$9,246
134,389
kWh
|
$1,760
-
kW-mo/yr
|
- | - | $(-4,800.0) | - | |
02 | 2.6212: Turn off equipment during breaks, reduce operating time | $5,025 | - |
$5,025
73,021
kWh
|
- | - | - | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,022 | $300 |
$4,219
61,320
kWh
|
$803
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.1122: Re-size charging openings or add a movable door on equipment | $11,905 | - | - | - | - |
$12,070
-
MMBtu
|
$(-165.0) | - | |
05 | 2.2414: Use waste heat from hot flue gases to preheat | $4,750 | $3,000 | - | - | - |
$4,750
-
MMBtu
|
- | - | |
06 | 2.8112: Combine utility meters | $63,547 | $50,000 | - | - | $63,547 | - | - | - | |
07 | 3.5316: Contract a wood pallet recycling company | $11,280 | - | - | - | - | - | - | $11,280 | |
TOTAL RECOMMENDED | $107,735 | $54,300 |
$18,490
268,730
kWh
|
$2,563
-
kW-mo/yr
|
$63,547 |
$16,820
-
MMBtu
|
$(-4,965.0) | $11,280 | ||
TOTAL IMPLEMENTED | $10,047 | $300 |
$9,244
134,341
kWh
|
$803
-
kW-mo/yr
|
- | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs