| Assessment Year | 2001 |
|---|---|
| Principal Product | Motor Vehicle Parts |
| NAICS |
n/a
|
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $10 M to 50M |
| # of Employees | 230 |
| Plant Area |
60,000
ft2
|
| Annual Production | 16,000,000
pieces
|
| Production Hrs. Annual | 2,400
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $43,421 | 1,562,120 |
kWh
|
$0.028 |
| Electricity Demand | $69,224 | 4,920 |
kW-mo/yr
|
$14.07 |
| Natural Gas | $12,702 | 2,086 |
MMBtu
|
$6.09 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $331,602 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.1161: Eliminate/reduce an operation | $252,000 | $75,000 | - | - | - | - | - | $252,000 | - | - | |
| 02 | 4.125: | $52,440 | $1,200 | - | - | - | - | - | $35,280 | - | $17,160 | |
| 03 | 2.4224: Upgrade controls on compressors | $10,581 | $12,000 |
$2,021
72,171
kWh
|
$6,247
-
kW-mo/yr
|
$2,313
-
MMBtu
|
- | - | - | - | - | |
| 04 | 3.5112: Reprocess spent oils on site for re-use | $12,893 | $3,200 | - | - | - |
$3,983
-
gal
|
- | - | $8,910 | - | |
| 05 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $1,612 | $3,000 | - | - | - | - |
$1,612
-
lb
|
- | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $944 | $2,412 |
$269
9,600
kWh
|
$675
-
kW-mo/yr
|
- | - | - | - | - | - | |
| 07 | 2.7124: Make a practice of turning off lights when not needed | $637 | - |
$181
6,480
kWh
|
$456
-
kW-mo/yr
|
- | - | - | - | - | - | |
| 08 | 2.7261: Install timers and/or thermostats | $495 | $1,200 |
$190
2,641
kWh
|
- |
$305
-
MMBtu
|
- | - | - | - | - | |
| TOTAL RECOMMENDED | $331,602 | $98,012 |
$2,661
90,892
kWh
|
$7,378
-
kW-mo/yr
|
$2,618
-
MMBtu
|
$3,983
-
gal
|
$1,612
-
lb
|
$287,280 | $8,910 | $17,160 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs