Assessment Year | 1991 |
---|---|
Principal Product | ENVELOPES |
NAICS |
n/a
|
SIC | 2677: Envelopes |
Sales Range | $1 M to 5M |
# of Employees | 220 |
Plant Area |
n/a
|
Annual Production | 750,000,000
pieces
|
Production Hrs. Annual | 6,640
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $226,483 | 4,946,952 |
kWh
|
$0.046 |
Natural Gas | $8,362 | 1,929 |
MMBtu
|
$4.33 |
LPG | $2,103 | 175 |
MMBtu
|
$12.02 |
Other Energy | $12,126 | 1,219 |
MMBtu
|
$9.95 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $13,399 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.3191: Use demand controller or load shedder | $2,222 | $3,000 |
$2,222
-
kWh
|
- | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $1,311 | $1,500 |
$1,311
56,272
kWh
|
- | - | |
03 | 2.2443: Re-use or recycle hot or cold process exhaust air | $4,426 | $7,600 | - |
$4,426
-
MMBtu
|
- | |
04 | 2.6232: Install set-back timers | $5,440 | - |
$4,427
189,918
kWh
|
- | $1,013 | |
TOTAL RECOMMENDED | $13,399 | $12,100 |
$7,960
246,190
kWh
|
$4,426
-
MMBtu
|
$1,013 | ||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs