ITAC Assessment: UD0320
ITAC logo
ITAC Assessment: UD0320
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product PARTS FOR AIRCRAFT
NAICS
n/a
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 151
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 6,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $67,861 1,286,342
kWh
LPG $1,449 177
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,490 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings LPG Savings Administrative Changes Savings
01 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $1,650 - $1,650
34,877
kWh
- -
02 2.6232: Install set-back timers $1,090 - $970
38,394
kWh
- $120
03 2.7261: Install timers and/or thermostats $1,389 $4,000 $945
37,515
kWh
$444
-
MMBtu
-
04 2.7224: Reduce space conditioning during non-working hours $1,361 $3,000 $1,361
27,257
kWh
- -
TOTAL RECOMMENDED $5,490 $7,000 $4,926
138,043
kWh
$444
-
MMBtu
$120
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs