| Assessment Year | 1990 |
|---|---|
| Principal Product | PRINTED MATERIALS |
| NAICS |
n/a
|
| SIC | 2721: Periodicals: Publishing, or Publishing and Printing |
| Sales Range | $10 M to 50M |
| # of Employees | 450 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $306,435 | 5,434,936 |
kWh
|
$0.056 |
| Natural Gas | $115,631 | 27,972 |
MMBtu
|
$4.13 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $30,624 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $13,274 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.8114: Change rate schedules or other changes in utility service | $13,076 | $18,000 |
$13,076
-
kWh
|
- | |
| 02 | 2.7261: Install timers and/or thermostats | $3,951 | $700 | - |
$3,951
-
MMBtu
|
|
| 03 | 2.7229: Air condition only space necessary | $1,295 | $200 | - |
$1,295
-
MMBtu
|
|
| 04 | 2.2437: Recover waste heat from equipment | $3,374 | $8,000 |
$2,049
20,809
kWh
|
$1,325
-
MMBtu
|
|
| 05 | 2.6232: Install set-back timers | $900 | $500 |
$1,019
14,068
kWh
|
$(-119.0)
-
MMBtu
|
|
| 06 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $8,028 | $10,000 |
$8,028
242,380
kWh
|
- | |
| TOTAL RECOMMENDED | $30,624 | $37,400 |
$24,172
277,257
kWh
|
$6,452
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $13,274 | $10,900 |
$8,028
242,380
kWh
|
$5,246
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs