ITAC Assessment: UD0221
ITAC logo
ITAC Assessment: UD0221
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product ELECTRICAL CONNECTORS
NAICS
n/a
SIC 3643: Current-Carrying Wiring Devices
Sales Range $10
M
to 50
M
# of Employees 350
Plant Area
n/a
Annual Production 8,000,000
lb
Production Hrs. Annual 4,800
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $332,077 5,517,292
kWh
Natural Gas $106,254 21,928
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $44,718 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $40,803

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.3511: Use plant owned transformers or lease transformers $3,915 $20,000 $8,715
-
kWh
- $(-4,800.0)
02 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $16,515 - - $16,515
-
MMBtu
-
03 2.2437: Recover waste heat from equipment $6,218 - $8,144
211,606
kWh
$(-1,926.0)
-
MMBtu
-
04 2.6242: Minimize operation of equipment maintained in standby condition $7,322 $10,000 $7,322
163,834
kWh
- -
05 2.7261: Install timers and/or thermostats $7,926 $9,000 - $7,926
-
MMBtu
-
06 2.7442: Keep doors and windows shut when not on use $2,822 $2,070 $2,870
83,236
kWh
$(-759.0)
-
MMBtu
$711
TOTAL RECOMMENDED $44,718 $41,070 $27,051
458,676
kWh
$21,756
-
MMBtu
$(-4,089.0)
TOTAL IMPLEMENTED $40,803 $21,070 $18,336
458,676
kWh
$21,756
-
MMBtu
$711
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs