| Assessment Year | 1985 |
|---|---|
| Principal Product | SOFT TRIM INTERIOR PARTS |
| NAICS |
n/a
|
| SIC | 2299: Textile goods, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 4,500
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $120,454 | 1,587,046 |
kWh
|
$0.076 |
| Natural Gas | $40,059 | 6,162 |
MMBtu
|
$6.50 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $5,024 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,024 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $812 | - |
$812
29,308
kWh
|
- | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $219 | $580 |
$219
3,224
kWh
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,687 | $218 |
$1,915
27,843
kWh
|
$(-228.0)
-
MMBtu
|
|
| 04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,961 | - |
$1,961
-
kWh
|
- | |
| 05 | 2.2437: Recover waste heat from equipment | $345 | $920 | - |
$345
-
MMBtu
|
|
| TOTAL RECOMMENDED | $5,024 | $1,718 |
$4,907
60,375
kWh
|
$117
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $5,024 | $1,718 |
$4,907
60,375
kWh
|
$117
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs