ITAC Assessment: UC2517
ITAC logo
ITAC Assessment: UC2517
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Wooden cabinets
NAICS 337212: Custom Architectural Woodwork and Millwork Manufacturing
SIC 2431: Millwork
Sales Range $10
M
to 50
M
# of Employees 50
Plant Area 68,000
ft2
Annual Production 7,800,000
units
Production Hrs. Annual 2,000
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $117,687 583,872
kWh
Electricity Demand $67,696 3,189
kW-mo/yr
Electricity Fees $31,810 -
LPG $5,219 113
MMBtu
Fuel Oil #1 $54,532 1,824
MMBtu
TOTAL YEARLY COSTS $276,945
RECOMMENDED SAVINGS* $77,130 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings LPG Savings
01 2.8114: Change rate schedules or other changes in utility service $17,808 - - - $17,808 -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,638 $340 $1,409
6,988
kWh
$229
-
kW-mo/yr
- -
03 2.4322: Use or replace with energy efficient substitutes $4,211 $30,300 - - - $4,211
-
MMBtu
04 2.4231: Reduce the pressure of compressed air to the minimum required $3,387 - $348
1,727
kWh
$3,039
-
kW-mo/yr
- -
05 2.4221: Install compressor air intakes in coolest locations $613 $950 $536
2,657
kWh
$77
-
kW-mo/yr
- -
06 2.4239: Eliminate or reduce compressed air usage $99 - $99
492
kWh
- - -
07 2.7232: Replace existing hvac unit with high efficiency model $47,694 $234,000 $24,592
121,986
kWh
$23,102
-
kW-mo/yr
- -
08 2.6231: Utilize controls to operate equipment only when needed $1,679 $75 $1,679
8,328
kWh
- - -
TOTAL RECOMMENDED $77,130 $265,665 $28,663
142,178
kWh
$26,448
-
kW-mo/yr
$17,808 $4,211
-
MMBtu
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings LPG Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs