Assessment Year | 2025 |
---|---|
Principal Product | Surgical supplies |
NAICS | 339113: Surgical Appliance and Supplies Manufacturing |
SIC | 3841: Surgical and Medical Instruments and Apparatus |
Sales Range | $50 M to 100M |
# of Employees | 107 |
Plant Area |
50,000
ft2
|
Annual Production | 1,000,000
units
|
Production Hrs. Annual | 2,800
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $65,743 | 416,215 |
kWh
|
$0.16 |
Electricity Demand | $33,755 | 1,294 |
kW-mo/yr
|
$26.09 |
Electricity Fees | $7,222 | - |
|
- |
Natural Gas | $11,197 | 906 |
MMBtu
|
$12.35 |
TOTAL YEARLY COSTS | $117,917 | |||
RECOMMENDED SAVINGS* | $17,845 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $621 | $198 |
$520
3,289
kWh
|
$102
-
kW-mo/yr
|
- | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $8,824 | $75 |
$6,489
41,069
kWh
|
$2,336
-
kW-mo/yr
|
- | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $928 | $870 |
$756
4,787
kWh
|
$171
-
kW-mo/yr
|
- | - | - | |
04 | 2.7261: Install timers and/or thermostats | $926 | $2,780 |
$185
1,170
kWh
|
- |
$1,141
-
MMBtu
|
- | $(-400.0) | |
05 | 2.8121: Apply for tax-free status for energy purchases | $6,546 | - | - | - | - | $6,546 | - | |
TOTAL RECOMMENDED | $17,845 | $3,923 |
$7,950
50,315
kWh
|
$2,608
-
kW-mo/yr
|
$1,141
-
MMBtu
|
$6,546 | $(-400.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs