Assessment Year | 2023 |
---|---|
Principal Product | Nameplate |
NAICS | 332812: Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers |
SIC | 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 67 |
Plant Area |
40,000
ft2
|
Annual Production | 29,000,000
units
|
Production Hrs. Annual | 2,750
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $75,654 | 711,680 |
kWh
|
$0.11 | |
Electricity Demand | $42,386 | 2,513 |
kW-mo/yr
|
$16.87 | |
Electricity Fees | $(-1,358.1) | - |
|
- | |
LPG | $36,337 | 1,634 |
MMBtu
|
$22.23 | |
Waste Disposal Costs | |||||
Water Usage | $4,651 | 632 |
Tgal
|
$7.36 | |
TOTAL YEARLY COSTS | $157,670 | ||||
RECOMMENDED SAVINGS* | $143,323 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $29,244 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $1,161 | $428 |
$953
8,970
kWh
|
$207
-
kW-mo/yr
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,426 | $1,300 |
$1,993
18,747
kWh
|
$433
-
kW-mo/yr
|
- | - | |
03 | 2.6231: Utilize controls to operate equipment only when needed | $6,502 | $150 |
$6,502
61,168
kWh
|
- | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $6,573 | $75 |
$5,399
50,789
kWh
|
$1,174
-
kW-mo/yr
|
- | - | |
05 | 2.6218: Turn off equipment when not in use | $9,710 | $1,062 |
$9,710
91,342
kWh
|
- | - | - | |
06 | 4.652: Replace existing equipment with more suitable substitutes | $1,947 | $9,514 |
$1,947
18,311
kWh
|
- | - | - | |
07 | 2.4226: Use / purchase optimum sized compressor | $1,620 | $19,500 |
$1,620
15,236
kWh
|
- | - | - | |
08 | 2.6242: Minimize operation of equipment maintained in standby condition | $1,522 | $500 |
$1,250
11,760
kWh
|
$272
-
kW-mo/yr
|
- | - | |
09 | 2.2511: Insulate bare equipment | $445 | $390 | - | - |
$445
-
MMBtu
|
- | |
10 | 4.212: Adopt in-house material generation | $54,436 | $125,322 |
$(-396.4)
(-3,728)
kWh
|
$(-86.2)
-
kW-mo/yr
|
- | $54,918 | |
11 | 2.7232: Replace existing hvac unit with high efficiency model | $892 | $2,151 |
$(-528.9)
(-4,976)
kWh
|
$(-115.0)
-
kW-mo/yr
|
$1,536
-
MMBtu
|
- | |
12 | 2.7232: Replace existing hvac unit with high efficiency model | $5,895 | $34,958 |
$(-3,889.0)
(-36,584)
kWh
|
$(-845.3)
-
kW-mo/yr
|
$10,629
-
MMBtu
|
- | |
13 | 2.9114: Use solar heat to make electricty | $50,197 | $515,729 |
$50,197
472,223
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $143,323 | $711,079 |
$74,757
703,258
kWh
|
$1,039
-
kW-mo/yr
|
$12,609
-
MMBtu
|
$54,918 | ||
TOTAL IMPLEMENTED | $29,244 | $24,737 |
$25,944
244,065
kWh
|
$1,763
-
kW-mo/yr
|
$1,536
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs