ITAC Assessment: UC2312
ITAC logo
ITAC Assessment: UC2312
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Nameplate
NAICS 332812: Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers
SIC 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 67
Plant Area 40,000
ft2
Annual Production 29,000,000
units
Production Hrs. Annual 2,750
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $75,654 711,680
kWh
Electricity Demand $42,386 2,513
kW-mo/yr
Electricity Fees $(-1,358.1) -
LPG $36,337 1,634
MMBtu
Waste Disposal Costs
Water Usage $4,651 632
Tgal
TOTAL YEARLY COSTS $157,670
RECOMMENDED SAVINGS* $143,323 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $29,244

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings Ancillary Material Cost Savings
01 2.4221: Install compressor air intakes in coolest locations $1,161 $428 $953
8,970
kWh
$207
-
kW-mo/yr
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,426 $1,300 $1,993
18,747
kWh
$433
-
kW-mo/yr
- -
03 2.6231: Utilize controls to operate equipment only when needed $6,502 $150 $6,502
61,168
kWh
- - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $6,573 $75 $5,399
50,789
kWh
$1,174
-
kW-mo/yr
- -
05 2.6218: Turn off equipment when not in use $9,710 $1,062 $9,710
91,342
kWh
- - -
06 4.652: Replace existing equipment with more suitable substitutes $1,947 $9,514 $1,947
18,311
kWh
- - -
07 2.4226: Use / purchase optimum sized compressor $1,620 $19,500 $1,620
15,236
kWh
- - -
08 2.6242: Minimize operation of equipment maintained in standby condition $1,522 $500 $1,250
11,760
kWh
$272
-
kW-mo/yr
- -
09 2.2511: Insulate bare equipment $445 $390 - - $445
-
MMBtu
-
10 4.212: Adopt in-house material generation $54,436 $125,322 $(-396.4)
(-3,728)
kWh
$(-86.2)
-
kW-mo/yr
- $54,918
11 2.7232: Replace existing hvac unit with high efficiency model $892 $2,151 $(-528.9)
(-4,976)
kWh
$(-115.0)
-
kW-mo/yr
$1,536
-
MMBtu
-
12 2.7232: Replace existing hvac unit with high efficiency model $5,895 $34,958 $(-3,889.0)
(-36,584)
kWh
$(-845.3)
-
kW-mo/yr
$10,629
-
MMBtu
-
13 2.9114: Use solar heat to make electricty $50,197 $515,729 $50,197
472,223
kWh
- - -
TOTAL RECOMMENDED $143,323 $711,079 $74,757
703,258
kWh
$1,039
-
kW-mo/yr
$12,609
-
MMBtu
$54,918
TOTAL IMPLEMENTED $29,244 $24,737 $25,944
244,065
kWh
$1,763
-
kW-mo/yr
$1,536
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs