Assessment Year | 2023 |
---|---|
Principal Product | Metal wires |
NAICS | 331420: Copper Rolling, Drawing, Extruding, and Alloying |
SIC | 3357: Drawing and Insulating of Nonferrous Wire |
Sales Range | $50 M to 100M |
# of Employees | 72 |
Plant Area |
105,000
ft2
|
Annual Production | 25,000,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $326,657 | 3,063,600 |
kWh
|
$0.11 |
Electricity Demand | $312,790 | 11,197 |
kW-mo/yr
|
$27.93 |
Electricity Fees | $45,387 | - |
|
- |
Natural Gas | $38,441 | 4,264 |
MMBtu
|
$9.02 |
TOTAL YEARLY COSTS | $723,274 | |||
RECOMMENDED SAVINGS* | $627,166 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $251,033 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $204,687 | $50,000 | - | - | $204,687 | - | - | - | |
02 | 2.8121: Apply for tax-free status for energy purchases | $41,561 | - | - | - | $41,561 | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,353 | $987 |
$888
8,328
kWh
|
$465
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.3311: Replace dc equipment with ac equipment | $55,687 | $171,637 |
$40,979
384,421
kWh
|
$14,708
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $1,549 | $428 |
$1,140
10,695
kWh
|
$409
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,434 | $300 |
$1,553
14,569
kWh
|
$881
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,525 | $1,300 |
$5,440
51,034
kWh
|
$3,085
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.7232: Replace existing hvac unit with high efficiency model | $5,939 | $27,365 |
$23
214
kWh
|
$8
-
kW-mo/yr
|
- |
$5,908
-
MMBtu
|
- | - | |
09 | 2.7261: Install timers and/or thermostats | $998 | $3,691 | - | - | - |
$998
-
MMBtu
|
- | - | |
10 | 4.212: Adopt in-house material generation | $207,659 | $464,727 |
$(-4,305.0)
(-40,384)
kWh
|
$(-4,998.6)
-
kW-mo/yr
|
- | - | - | $216,963 | |
11 | 4.454: Modify startup/shutdown times | $11,360 | $7,140 | - |
$11,360
-
kW-mo/yr
|
- | - | - | - | |
12 | 2.9114: Use solar heat to make electricty | $85,414 | $609,968 |
$97,435
914,028
kWh
|
- | - | - | $(-12,021.0) | - | |
TOTAL RECOMMENDED | $627,166 | $1,337,543 |
$143,153
1,342,904
kWh
|
$25,917
-
kW-mo/yr
|
$246,248 |
$6,906
-
MMBtu
|
$(-12,021.0) | $216,963 | ||
TOTAL IMPLEMENTED | $251,033 | $54,978 |
$2,441
22,897
kWh
|
$1,346
-
kW-mo/yr
|
$246,248 |
$998
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs