| Assessment Year | 2025 |
|---|---|
| Principal Product | Metal Brackets |
| NAICS | 336370: Motor Vehicle Metal Stamping |
| SIC | 3465: Automotive Stampings |
| Sales Range | $10 M to 50M |
| # of Employees | 145 |
| Plant Area |
160,000
ft2
|
| Annual Production | 433,333
units
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | Alabama |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $593,932 | 5,930,481 |
kWh
|
$0.10 |
| Electricity Fees | $256 | - |
|
- |
| Natural Gas | $9,825 | 564 |
MMBtu
|
$17.42 |
| TOTAL YEARLY COSTS | $604,013 | |||
| RECOMMENDED SAVINGS* | $56,676 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,742 | $32,193 |
$13,737
137,232
kWh
|
$5 | - | |
| 02 | 2.7442: Keep doors and windows shut when not on use | $13,247 | $2,208 |
$11,281
112,697
kWh
|
$5 |
$1,961
-
MMBtu
|
|
| 03 | 2.7261: Install timers and/or thermostats | $10,720 | $241 |
$10,716
107,052
kWh
|
$4 | - | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,103 | $10,944 |
$5,101
50,956
kWh
|
$2 | - | |
| 05 | 2.6218: Turn off equipment when not in use | $7,332 | $4,020 |
$7,329
73,221
kWh
|
$3 | - | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,885 | $2,349 |
$2,884
28,808
kWh
|
$1 | - | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,647 | $7,759 |
$3,646
36,422
kWh
|
$1 | - | |
| TOTAL RECOMMENDED | $56,676 | $59,714 |
$54,694
546,388
kWh
|
$21 |
$1,961
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs