Assessment Year | 2014 |
---|---|
Principal Product | Metal/Plastic Automotive Parts |
NAICS | 336370: Motor Vehicle Metal Stamping |
SIC | 3363: Aluminum Die-Castings |
Sales Range | $10 M to 50M |
# of Employees | 296 |
Plant Area |
155,000
ft2
|
Annual Production | 336,000,000
units
|
Production Hrs. Annual | 6,336
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $708,345 | 12,758,817 |
kWh
|
$0.056 |
Electricity Demand | $156,155 | 32,071 |
kW-mo/yr
|
$4.87 |
Electricity Fees | $99,946 | - |
|
- |
Natural Gas | $4,467 | 342 |
MMBtu
|
$13.06 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $114,182 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,621 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $57,076 | $122,855 |
$46,050
829,433
kWh
|
$7,651
-
kW-mo/yr
|
$3,375 | - | |
02 | 2.7122: Disconnect ballasts | $14,055 | $1,200 |
$11,229
202,246
kWh
|
$1,866
-
kW-mo/yr
|
$960 | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $8,580 | $6,440 |
$7,994
143,989
kWh
|
- | $586 | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,605 | $6,195 |
$6,170
111,134
kWh
|
$916
-
kW-mo/yr
|
$519 | - | |
05 | 2.7442: Keep doors and windows shut when not on use | $3,304 | $583 |
$3,078
55,447
kWh
|
- | $226 | - | |
06 | 2.7261: Install timers and/or thermostats | $4,317 | $625 |
$2,489
44,824
kWh
|
- | $182 |
$1,646
-
MMBtu
|
|
07 | 2.3212: Optimize plant power factor | $19,245 | $19,520 | - | - | $19,245 | - | |
TOTAL RECOMMENDED | $114,182 | $157,418 |
$77,010
1,387,073
kWh
|
$10,433
-
kW-mo/yr
|
$25,093 |
$1,646
-
MMBtu
|
||
TOTAL IMPLEMENTED | $7,621 | $1,208 |
$5,567
100,271
kWh
|
- | $408 |
$1,646
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs