Assessment Year | 2012 |
---|---|
Principal Product | Trailers |
NAICS | 336212: Truck Trailer Manufacturing |
SIC | 3715: Truck Trailers |
Sales Range | $5 M to 10M |
# of Employees | 98 |
Plant Area |
130,000
ft2
|
Annual Production | 1,275
pieces
|
Production Hrs. Annual | 2,288
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $102,650 | 1,513,600 |
kWh
|
$0.068 |
Electricity Demand | $76,516 | 7,124 |
kW-mo/yr
|
$10.74 |
Electricity Fees | $10,281 | - |
|
- |
Natural Gas | $69,783 | 6,187 |
MMBtu
|
$11.28 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $22,235 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,301 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,718 | $480 |
$2,795
41,214
kWh
|
$1,698
-
kW-mo/yr
|
$225 | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,736 | $2,500 |
$1,543
22,746
kWh
|
$110
-
kW-mo/yr
|
$83 | - | |
03 | 2.4226: Use / purchase optimum sized compressor | $2,094 | $1,680 |
$2,394
35,301
kWh
|
$(-400.0)
-
kW-mo/yr
|
$100 | - | |
04 | 2.2437: Recover waste heat from equipment | $1,815 | $539 | - | - | $70 |
$1,745
-
MMBtu
|
|
05 | 2.7231: Use radiant heater for spot heating | $4,712 | $4,728 | - | - | $181 |
$4,531
-
MMBtu
|
|
06 | 2.7261: Install timers and/or thermostats | $5,313 | $2,040 |
$5,060
74,614
kWh
|
- | $253 | - | |
07 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,847 | $2 |
$1,759
25,937
kWh
|
- | $88 | - | |
TOTAL RECOMMENDED | $22,235 | $11,969 |
$13,551
199,812
kWh
|
$1,408
-
kW-mo/yr
|
$1,000 |
$6,276
-
MMBtu
|
||
TOTAL IMPLEMENTED | $8,301 | $2,982 |
$6,097
89,897
kWh
|
$1,808
-
kW-mo/yr
|
$396 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs