| Assessment Year | 2003 |
|---|---|
| Principal Product | Coating Automotive Parts |
| NAICS | 332812: Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers |
| SIC | 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 35 |
| Plant Area |
486,530
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 2,280
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $131,042 | 1,902,511 |
kWh
|
$0.069 |
| Electricity Demand | $82,877 | 6,588 |
kW-mo/yr
|
$12.58 |
| Electricity Fees | $(-6,041.0) | - |
|
- |
| Natural Gas | $17,512 | 3,514 |
MMBtu
|
$4.98 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $25,354 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $18,914 | $100,000 |
$19,568
284,000
kWh
|
$5,396
-
kW-mo/yr
|
$(-6,050.0)
-
MMBtu
|
|
| 02 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $2,030 | $5,280 | - | - |
$2,030
-
MMBtu
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,440 | $6,423 |
$1,032
14,986
kWh
|
$1,408
-
kW-mo/yr
|
- | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,970 | $300 |
$1,272
18,464
kWh
|
$698
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $25,354 | $112,003 |
$21,872
317,450
kWh
|
$7,502
-
kW-mo/yr
|
$(-4,020.0)
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs