ITAC Assessment: AS0286
ITAC logo
ITAC Assessment: AS0286
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Flat Circuits and Flex board
NAICS
n/a
SIC 3678: Electronic Connectors
Sales Range $100
M
to 500
M
# of Employees 300
Plant Area 150,000
ft2
Annual Production 100,000
pieces
Production Hrs. Annual 8,568
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $772,676 16,445,194
kWh
Electricity Fees $140,854 -
Natural Gas $132,086 23,111
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $37,507 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,045 $382 $3,645
115,182
kWh
$400
-
kW-mo/yr
- - - - -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $6,469 $3,800 $5,814
183,763
kWh
$655
-
kW-mo/yr
- - - - -
03 2.4133: Use most efficient type of electric motors $4,073 $6,959 $3,711
104,338
kWh
$362
-
kW-mo/yr
- - - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $407 $609 $217
6,741
kWh
$17
-
kW-mo/yr
- - $86 - $87
05 2.4231: Reduce the pressure of compressed air to the minimum required $10,262 $120 $10,262
324,736
kWh
- - - - - -
06 3.6192: Use a less expensive method of waste removal $1,244 $120 - - - - - $1,244 -
07 3.5316: Contract a wood pallet recycling company $576 $60 - - - $576
-
lb
- - -
08 3.5313: Increase amount of waste recovered for resale $4,509 $780 - - $5,836
-
gal
- $(-1,327.0) - -
09 4.446: Automate finishing process $5,355 $1,500 - - - - $5,355 - -
10 4.454: Modify startup/shutdown times $567 $120 - - - - - $567 -
TOTAL RECOMMENDED $37,507 $14,450 $23,649
734,760
kWh
$1,434
-
kW-mo/yr
$5,836
-
gal
$576
-
lb
$4,114 $1,811 $87
TOTAL IMPLEMENTED - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs