ITAC Assessment: TT0250
ITAC logo
ITAC Assessment: TT0250
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Walk-in Coolers/Freezers and Refrigeration Systems
NAICS 333415: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipmen
SIC 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment
Sales Range $50
M
to 100
M
# of Employees 272
Plant Area 145,162
ft2
Annual Production 540,000
units
Production Hrs. Annual 2,600
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $86,151 1,096,800
kWh
Electricity Demand $42,538 4,114
kW-mo/yr
Natural Gas $17,540 1,681
MMBtu
LPG $15,891 519
MMBtu
Waste Disposal Costs
Water Usage $3,226 3,811
Tgal
Water Disposal $2,242 3,810
Tgal
Other Liquid (non-haz) $14,066 474,976
gal
Gaseous Waste $90,000 15,000
lb
TOTAL YEARLY COSTS $271,654
RECOMMENDED SAVINGS* $37,122 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $29,072

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings Other Liquid (non-haz) Savings Gaseous Waste Savings Administrative Changes Savings
01 2.8226: Increase efficiency of trucks $17,586 - $(-2,465.0)
(-31,200)
kWh
- - $15,891
-
MMBtu
- - $4,160
02 2.7232: Replace existing hvac unit with high efficiency model $6,326 $27,000 $6,326
80,586
kWh
- - - - - -
03 2.6212: Turn off equipment during breaks, reduce operating time $5,205 $3,000 $5,205
66,306
kWh
- - - - - -
04 2.4156: Establish a preventative maintenance program $2,240 $4,500 - - $530
-
MMBtu
- $710
-
gal
$1,000
-
lb
-
05 2.7261: Install timers and/or thermostats $1,600 $160 $1,600
20,382
kWh
- - - - - -
06 2.4224: Upgrade controls on compressors $1,587 $3,500 $987
12,576
kWh
$600
-
kW-mo/yr
- - - - -
07 2.4153: Avoid emergency rewind of motors $1,333 $400 - - - - - - $1,333
08 2.7135: Install occupancy sensors $1,245 $1,068 $1,245
15,800
kWh
- - - - - -
TOTAL RECOMMENDED $37,122 $39,628 $12,898
164,450
kWh
$600
-
kW-mo/yr
$530
-
MMBtu
$15,891
-
MMBtu
$710
-
gal
$1,000
-
lb
$5,493
TOTAL IMPLEMENTED $29,072 $35,400 $4,848
61,962
kWh
$600
-
kW-mo/yr
$530
-
MMBtu
$15,891
-
MMBtu
$710
-
gal
$1,000
-
lb
$5,493
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings Other Liquid (non-haz) Savings Gaseous Waste Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs