Assessment Year | 2017 |
---|---|
Principal Product | Axle Assemblies |
NAICS | 331523: Nonferrous Metal Die-Casting Foundries |
SIC | 3363: Aluminum Die-Castings |
Sales Range | $100 M to 500M |
# of Employees | 134 |
Plant Area |
103,000
ft2
|
Annual Production | 96,000
units
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $75,964 | 998,400 |
kWh
|
$0.076 | |
Electricity Demand | $23,154 | 2,513 |
kW-mo/yr
|
$9.21 | |
Natural Gas | $7,012 | 853 |
MMBtu
|
$8.22 | |
Waste Disposal Costs | |||||
Solid Waste (non-haz) | $30,000 | 315,640 |
lb
|
$0.095 | |
TOTAL YEARLY COSTS | $136,130 | ||||
RECOMMENDED SAVINGS* | $45,919 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $37,784 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 3.1191: Change procedures / equipment / operating conditions | $33,156 | $94,000 | - | - | - |
$33,156
-
lb
|
|
02 | 2.6218: Turn off equipment when not in use | $4,274 | $3,000 |
$4,274
56,160
kWh
|
- | - | - | |
03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $3,861 | $10,500 |
$2,510
32,980
kWh
|
- |
$1,351
-
MMBtu
|
- | |
04 | 2.7135: Install occupancy sensors | $3,453 | $8,274 |
$3,411
44,822
kWh
|
$42
-
kW-mo/yr
|
- | - | |
05 | 2.7261: Install timers and/or thermostats | $1,175 | $250 |
$634
8,333
kWh
|
- |
$541
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $45,919 | $116,024 |
$10,829
142,295
kWh
|
$42
-
kW-mo/yr
|
$1,892
-
MMBtu
|
$33,156
-
lb
|
||
TOTAL IMPLEMENTED | $37,784 | $102,524 |
$4,045
53,155
kWh
|
$42
-
kW-mo/yr
|
$541
-
MMBtu
|
$33,156
-
lb
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs