Assessment Year | 2007 |
---|---|
Principal Product | Engineered Chain Products |
NAICS | 333613: Mechanical Power Transmission Equipment Manufacturing |
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 245 |
Plant Area |
200,000
ft2
|
Annual Production | 720
thousand feet
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $516,183 | 8,990,400 |
kWh
|
$0.057 |
Electricity Demand | $229,580 | 19,519 |
kW-mo/yr
|
$11.76 |
Electricity Fees | $7,779 | - |
|
- |
Natural Gas | $648,753 | 64,793 |
MMBtu
|
$10.01 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $157,951 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $28,770 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2611: Moderate cooling tower outlet temperature | $2,856 | $3,500 |
$2,603
72,515
kWh
|
$253
-
kW-mo/yr
|
- | - | |
02 | 2.2615: Clean condenser tubes | $1 | $26,405 | - | - | - | $1 | |
03 | 2.7261: Install timers and/or thermostats | $1,270 | - |
$1,270
30,825
kWh
|
- | - | - | |
04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $41,993 | - | - | - |
$41,993
-
MMBtu
|
- | |
05 | 2.2531: Re-size charging openings or add movable cover or door | $9,800 | - | - | - |
$9,800
-
MMBtu
|
- | |
06 | 2.2531: Re-size charging openings or add movable cover or door | $1,850 | $3,000 | - | - |
$1,850
-
MMBtu
|
- | |
07 | 2.2531: Re-size charging openings or add movable cover or door | $1,360 | $1,500 | - | - |
$1,360
-
MMBtu
|
- | |
08 | 2.4239: Eliminate or reduce compressed air usage | $1,770 | - |
$1,770
42,092
kWh
|
- | - | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,290 | $1,000 |
$11,290
274,026
kWh
|
- | - | - | |
10 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $29,038 | - |
$29,038
351,917
kWh
|
- | - | - | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $45,200 | - |
$45,200
1,590
kWh
|
- | - | - | |
12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,715 | $11,979 |
$10,715
147,700
kWh
|
- | - | - | |
13 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $698 | $600 |
$698
292
kWh
|
- | - | - | |
14 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $110 | - |
$110
315
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $157,951 | $47,984 |
$102,694
921,272
kWh
|
$253
-
kW-mo/yr
|
$55,003
-
MMBtu
|
$1 | ||
TOTAL IMPLEMENTED | $28,770 | $47,984 |
$25,306
494,533
kWh
|
$253
-
kW-mo/yr
|
$3,210
-
MMBtu
|
$1 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs