ITAC Assessment: TR0020
ITAC logo
ITAC Assessment: TR0020
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product stamped metal parts
NAICS 332111: Iron and Steel Forging
SIC 3462: Iron and Steel Forgings
Sales Range $10
M
to 50
M
# of Employees 50
Plant Area 344,124
ft2
Annual Production 693,500
pieces
Production Hrs. Annual 4,200
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $55,133 1,206,258
kWh
Electricity Demand $47,084 4,605
kW-mo/yr
Electricity Fees $3,364 -
TOTAL YEARLY COSTS $105,581
RECOMMENDED SAVINGS* $53,968 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $28,688

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Ancillary Material Cost Savings
01 2.7111: Reduce illumination to minimum necessary levels $1,021 - $1,002
8,808
kWh
- $19 -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,748 - $616
13,480
kWh
$1,132
-
kW-mo/yr
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $558 $150 $154
3,364
kWh
$47
-
kW-mo/yr
- $357
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $12,914 $3,155 $7,880
172,421
kWh
$5,035
-
kW-mo/yr
- -
05 2.7447: Install vinyl strip / high speed / air curtain doors $12,445 $810 $7,537
164,913
kWh
$4,909
-
kW-mo/yr
- -
06 2.9114: Use solar heat to make electricty $25,280 $40,101 $25,280
553,173
kWh
- - -
TOTAL RECOMMENDED $53,968 $44,216 $42,468
916,159
kWh
$11,123
-
kW-mo/yr
$19 $357
TOTAL IMPLEMENTED $28,688 $4,115 $17,188
362,986
kWh
$11,123
-
kW-mo/yr
$19 $357
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs