Assessment Year | 2000 |
---|---|
Principal Product | transformers |
NAICS |
n/a
|
SIC | 3612: Power, Distribution, and Specialty Transformers |
Sales Range | $50 M to 100M |
# of Employees | 250 |
Plant Area |
260,000
ft2
|
Annual Production | 1,902
pieces
|
Production Hrs. Annual | 4,845
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $93,598 | 1,970,985 |
kWh
|
$0.047 |
Electricity Demand | $34,947 | 5,522 |
kW-mo/yr
|
$6.33 |
Natural Gas | $35,778 | 7,156 |
MMBtu
|
$5.00 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $53,088 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $40,857 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 3.2111: Install redundant equipment to avoid losses caused by equipment failure and routine maintenance | $25,255 | $1,075 |
$880
9,672
kWh
|
- | - | - | - | $24,375 | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,703 | $750 |
$6,447
137,163
kWh
|
$256
-
kW-mo/yr
|
- | - | - | - | |
03 | 3.4113: Treat and reuse rinse waters | $6,496 | $14,340 | - | - | - |
$916
-
Tgal
|
$5,580
-
gal
|
- | |
04 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $4,210 | $820 | - | - | - | - |
$4,210
-
gal
|
- | |
05 | 2.7444: Close holes and openings in building such as broken windows | $3,280 | $2,925 |
$3,280
135,404
kWh
|
- | - | - | - | - | |
06 | 2.7261: Install timers and/or thermostats | $2,289 | $2,150 |
$320
6,741
kWh
|
- |
$1,969
-
MMBtu
|
- | - | - | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,680 | $350 |
$1,000
36,928
kWh
|
$680
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.2511: Insulate bare equipment | $1,562 | $188 | - | - |
$1,562
-
MMBtu
|
- | - | - | |
09 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $893 | $2,950 | - | - |
$893
-
MMBtu
|
- | - | - | |
10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $720 | - |
$420
15,533
kWh
|
$300
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $53,088 | $25,548 |
$12,347
341,441
kWh
|
$1,236
-
kW-mo/yr
|
$4,424
-
MMBtu
|
$916
-
Tgal
|
$9,790
-
gal
|
$24,375 | ||
TOTAL IMPLEMENTED | $40,857 | $5,145 |
$9,067
206,037
kWh
|
$1,236
-
kW-mo/yr
|
$1,969
-
MMBtu
|
- |
$4,210
-
gal
|
$24,375 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs