Assessment Year | 1996 |
---|---|
Principal Product | Dyed and finished broad woven cloth |
NAICS |
n/a
|
SIC | 2269: Finishers of Textiles, Not elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 160 |
Plant Area |
115,000
ft2
|
Annual Production | 120,000
thousand feet
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | South Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $265,978 | 5,380,422 |
kWh
|
$0.049 |
Electricity Demand | $45,870 | 11,944 |
kW-mo/yr
|
$3.84 |
Natural Gas | $324,629 | 86,043 |
MMBtu
|
$3.77 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $28,605 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,015 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 3.6112: Use filter and drying oven to reduce sludge volume | $18,501 | $38,600 | - | - |
$(-32,930.0)
-
MMBtu
|
$39,431
-
lb
|
$12,000 | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,167 | $5,110 |
$4,122
84,115
kWh
|
$1,045
-
kW-mo/yr
|
- | - | - | |
03 | 2.7261: Install timers and/or thermostats | $3,848 | $520 |
$3,848
78,546
kWh
|
- | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $811 | $394 |
$431
8,792
kWh
|
$380
-
kW-mo/yr
|
- | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $278 | $170 |
$230
4,689
kWh
|
$48
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $28,605 | $44,794 |
$8,631
176,142
kWh
|
$1,473
-
kW-mo/yr
|
$(-32,930.0)
-
MMBtu
|
$39,431
-
lb
|
$12,000 | ||
TOTAL IMPLEMENTED | $9,015 | $5,630 |
$7,970
162,661
kWh
|
$1,045
-
kW-mo/yr
|
- | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs