ITAC Assessment: TN0580
ITAC logo
ITAC Assessment: TN0580
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Dyed and finished broad woven cloth
NAICS
n/a
SIC 2269: Finishers of Textiles, Not elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 160
Plant Area 115,000
ft2
Annual Production 120,000
thousand feet
Production Hrs. Annual 6,000
hrs
Location (State) South Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $265,978 5,380,422
kWh
Electricity Demand $45,870 11,944
kW-mo/yr
Natural Gas $324,629 86,043
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $28,605 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,015

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 3.6112: Use filter and drying oven to reduce sludge volume $18,501 $38,600 - - $(-32,930.0)
-
MMBtu
$39,431
-
lb
$12,000
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $5,167 $5,110 $4,122
84,115
kWh
$1,045
-
kW-mo/yr
- - -
03 2.7261: Install timers and/or thermostats $3,848 $520 $3,848
78,546
kWh
- - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $811 $394 $431
8,792
kWh
$380
-
kW-mo/yr
- - -
05 2.4221: Install compressor air intakes in coolest locations $278 $170 $230
4,689
kWh
$48
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $28,605 $44,794 $8,631
176,142
kWh
$1,473
-
kW-mo/yr
$(-32,930.0)
-
MMBtu
$39,431
-
lb
$12,000
TOTAL IMPLEMENTED $9,015 $5,630 $7,970
162,661
kWh
$1,045
-
kW-mo/yr
- - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs