ITAC Assessment: IC0080
ITAC logo
ITAC Assessment: IC0080
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Brake Parts
NAICS 336510: Railroad Rolling Stock Manufacturing
SIC 3531: Construction Machinery and Equipment
Sales Range $10
M
to 50
M
# of Employees 85
Plant Area 450,000
ft2
Annual Production 175,000
pieces
Production Hrs. Annual 3,920
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $200,200 3,967,633
kWh
Electricity Demand $116,772 10,429
kW-mo/yr
Electricity Fees $17,960 -
Natural Gas $170,105 29,944
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $145,508 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $117,212

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,301 $900 $1,330
63,380
kWh
$971
-
kW-mo/yr
- - - - -
02 2.4239: Eliminate or reduce compressed air usage $5,280 $10,420 $5,280
251,439
kWh
- - - - - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,046 - $605
28,814
kWh
$441
-
kW-mo/yr
- - - - -
04 2.2124: Install de-aerator in place of condensate tank $40,931 $95,360 - - $40,689
-
MMBtu
- - - $242
-
Tgal
05 2.1233: Analyze flue gas for proper air/fuel ratio $3,354 $2,640 - - $3,354
-
MMBtu
- - - -
06 2.2211: Use optimum temperature $24,757 $53,496 $(-563.0)
(-27,102)
kWh
$(-811.0)
-
kW-mo/yr
$26,719
-
MMBtu
$(-588.0) - - -
07 2.2211: Use optimum temperature $62,610 $35,948 - - $77,610
-
MMBtu
- $(-15,000.0) - -
08 2.7261: Install timers and/or thermostats $377 $1,384 - - $377
-
MMBtu
- - - -
09 2.7493: Use double or triple glazed windows to maintain higher relative humidity and to reduce heat losses $1,154 $10,967 - - $1,154
-
MMBtu
- - - -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $2,008 $11,878 $552
26,141
kWh
$855
-
kW-mo/yr
- $122 - $479 -
11 2.7142: Utilize higher efficiency lamps and/or ballasts $413 $1,540 $126
6,037
kWh
$199
-
kW-mo/yr
- - - $88 -
12 2.7142: Utilize higher efficiency lamps and/or ballasts $787 $896 $59
2,821
kWh
$42
-
kW-mo/yr
- $264 - $422 -
13 2.4111: Utilize energy-efficient belts and other improved mechanisms $232 $49 $90
4,281
kWh
$142
-
kW-mo/yr
- - - - -
14 2.6212: Turn off equipment during breaks, reduce operating time $258 - $100
4,766
kWh
$158
-
kW-mo/yr
- - - - -
TOTAL RECOMMENDED $145,508 $225,478 $7,579
360,577
kWh
$1,997
-
kW-mo/yr
$149,903
-
MMBtu
$(-202.0) $(-15,000.0) $989 $242
-
Tgal
TOTAL IMPLEMENTED $117,212 $147,753 $7,590
361,538
kWh
$1,953
-
kW-mo/yr
$121,653
-
MMBtu
$264 $(-15,000.0) $510 $242
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs