| Assessment Year | 1995 |
|---|---|
| Principal Product | Remanufactured mining equipment |
| NAICS |
n/a
|
| SIC | 3532: Mining Machinery and Equipment, Except Oil and Gas Field Machinery and Equipment |
| Sales Range | $10 M to 50M |
| # of Employees | 160 |
| Plant Area |
65,000
ft2
|
| Annual Production | 110
pieces
|
| Production Hrs. Annual | 7,344
hrs
|
| Location (State) | Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $101,659 | 2,339,390 |
kWh
|
$0.043 |
| Natural Gas | $51,221 | 10,205 |
MMBtu
|
$5.02 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $124,904 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $110,155 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7224: Reduce space conditioning during non-working hours | $5,841 | $1,550 |
$5,841
176,729
kWh
|
- | - | - | |
| 02 | 2.7261: Install timers and/or thermostats | $2,110 | $900 |
$2,110
105,510
kWh
|
- | - | - | |
| 03 | 2.4314: Use synthetic lubricant | $349 | - |
$349
6,741
kWh
|
- | - | - | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $260 | $540 |
$260
4,982
kWh
|
- | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $557 | $87 |
$557
10,551
kWh
|
- | - | - | |
| 06 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,317 | - |
$2,317
-
kWh
|
- | - | - | |
| 07 | 3.2121: Convert to electrostatic powder coating | $75,665 | $27,400 | - | - | - |
$75,665
-
lb
|
|
| 08 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $25,775 | $8,640 | - | - |
$25,775
-
lb
|
- | |
| 09 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $8,685 | $8,500 | - |
$8,685
-
gal
|
- | - | |
| 10 | 3.7131: Use a rag recycle service | $3,345 | - | - | - |
$3,345
-
lb
|
- | |
| TOTAL RECOMMENDED | $124,904 | $47,617 |
$11,434
304,513
kWh
|
$8,685
-
gal
|
$29,120
-
lb
|
$75,665
-
lb
|
||
| TOTAL IMPLEMENTED | $110,155 | $37,677 |
$8,715
187,280
kWh
|
- |
$25,775
-
lb
|
$75,665
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs