Assessment Year | 1995 |
---|---|
Principal Product | Precious metal chemical catalysts |
NAICS |
n/a
|
SIC | 3341: Secondary Smelting and Refining of Nonferrous Metals |
Sales Range | $10 M to 50M |
# of Employees | 220 |
Plant Area |
215,000
ft2
|
Annual Production | 4,000,000
lb
|
Production Hrs. Annual | 7,956
hrs
|
Location (State) | South Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $942,394 | 21,542,204 |
kWh
|
$0.044 |
Natural Gas | $775,160 | 202,807 |
MMBtu
|
$3.82 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $210,058 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,726 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $22,299 | $15,600 |
$22,299
261,430
kWh
|
- | - | - | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $19,726 | - |
$19,726
230,070
kWh
|
- | - | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,969 | $3,000 |
$10,969
127,784
kWh
|
- | - | - | - | - | |
04 | 2.2153: Close off unneeded steam lines | $1,642 | - | - |
$1,642
-
MMBtu
|
- | - | - | - | |
05 | 2.7132: Install timers on light switches in little used areas | $2,743 | $4,800 |
$2,743
68,581
kWh
|
- | - | - | - | - | |
06 | 2.6231: Utilize controls to operate equipment only when needed | $2,345 | $950 |
$2,345
58,617
kWh
|
- | - | - | - | - | |
07 | 2.4314: Use synthetic lubricant | $4,427 | - |
$4,427
50,996
kWh
|
- | - | - | - | - | |
08 | 2.2211: Use optimum temperature | $597 | - | - |
$597
-
MMBtu
|
- | - | - | - | |
09 | 2.8113: Purchase gas directly from a contract gas supplier | $77,516 | - | - | - | - | - | - | $77,516 | |
10 | 3.5131: Recycle white water | $32,232 | $31,600 | - | - |
$32,232
-
Tgal
|
- | - | - | |
11 | 3.6112: Use filter and drying oven to reduce sludge volume | $25,642 | $38,600 | - | - | - |
$25,642
-
lb
|
- | - | |
12 | 3.1191: Change procedures / equipment / operating conditions | $9,920 | - | - | - | - | - |
$9,920
-
lb
|
- | |
TOTAL RECOMMENDED | $210,058 | $94,550 |
$62,509
797,478
kWh
|
$2,239
-
MMBtu
|
$32,232
-
Tgal
|
$25,642
-
lb
|
$9,920
-
lb
|
$77,516 | ||
TOTAL IMPLEMENTED | $19,726 | - |
$19,726
230,070
kWh
|
- | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs