ITAC Assessment: UF0511
ITAC logo
ITAC Assessment: UF0511
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Reclaimed Water and Bio-Solids
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range $50
M
to 100
M
# of Employees 65
Plant Area 2,494,796
ft2
Annual Production 6,413,787,000
units
Production Hrs. Annual 8,760
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $372,332 18,074,400
kWh
Electricity Demand $524,061 40,584
kW-mo/yr
Electricity Fees $413,655 -
Natural Gas $572,444 60,667
MMBtu
TOTAL YEARLY COSTS $1,882,492
RECOMMENDED SAVINGS* $6,501,509 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $503,254

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Gas Savings Solid Waste (non-haz) Savings
01 2.1336: Install equipment to utilize waste fuel $5,783,172 $13,354,800 - - $572,444
-
MMBtu
$5,210,728
-
MMBtu
-
02 2.2414: Use waste heat from hot flue gases to preheat $200,909 $20,000 - - $200,909
-
MMBtu
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $9,022 $14,000 $2,947
143,080
kWh
$6,074
-
kW-mo/yr
- - -
04 2.6231: Utilize controls to operate equipment only when needed $7,447 $20,214 $7,447
361,488
kWh
- - - -
05 2.1233: Analyze flue gas for proper air/fuel ratio $5,152 $2,800 - - $5,152
-
MMBtu
- -
06 4.122: Develop standard procedures to improve internal yields $495,807 $1,875,550 $(-2,255.7)
(-109,500)
kWh
$(-1,937.0)
-
kW-mo/yr
- - $500,000
-
lb
TOTAL RECOMMENDED $6,501,509 $15,287,364 $8,139
395,068
kWh
$4,137
-
kW-mo/yr
$778,505
-
MMBtu
$5,210,728
-
MMBtu
$500,000
-
lb
TOTAL IMPLEMENTED $503,254 $1,895,764 $5,191
251,988
kWh
$(-1,937.0)
-
kW-mo/yr
- - $500,000
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Gas Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs