Assessment Year | 2017 |
---|---|
Principal Product | Reclaimed Water and Bio-Solids |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $50 M to 100M |
# of Employees | 65 |
Plant Area |
2,494,796
ft2
|
Annual Production | 6,413,787,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $372,332 | 18,074,400 |
kWh
|
$0.021 |
Electricity Demand | $524,061 | 40,584 |
kW-mo/yr
|
$12.91 |
Electricity Fees | $413,655 | - |
|
- |
Natural Gas | $572,444 | 60,667 |
MMBtu
|
$9.44 |
TOTAL YEARLY COSTS | $1,882,492 | |||
RECOMMENDED SAVINGS* | $6,501,509 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $503,254 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Gas Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.1336: Install equipment to utilize waste fuel | $5,783,172 | $13,354,800 | - | - |
$572,444
-
MMBtu
|
$5,210,728
-
MMBtu
|
- | |
02 | 2.2414: Use waste heat from hot flue gases to preheat | $200,909 | $20,000 | - | - |
$200,909
-
MMBtu
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,022 | $14,000 |
$2,947
143,080
kWh
|
$6,074
-
kW-mo/yr
|
- | - | - | |
04 | 2.6231: Utilize controls to operate equipment only when needed | $7,447 | $20,214 |
$7,447
361,488
kWh
|
- | - | - | - | |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $5,152 | $2,800 | - | - |
$5,152
-
MMBtu
|
- | - | |
06 | 4.122: Develop standard procedures to improve internal yields | $495,807 | $1,875,550 |
$(-2,255.7)
(-109,500)
kWh
|
$(-1,937.0)
-
kW-mo/yr
|
- | - |
$500,000
-
lb
|
|
TOTAL RECOMMENDED | $6,501,509 | $15,287,364 |
$8,139
395,068
kWh
|
$4,137
-
kW-mo/yr
|
$778,505
-
MMBtu
|
$5,210,728
-
MMBtu
|
$500,000
-
lb
|
||
TOTAL IMPLEMENTED | $503,254 | $1,895,764 |
$5,191
251,988
kWh
|
$(-1,937.0)
-
kW-mo/yr
|
- | - |
$500,000
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Gas Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs