Assessment Year | 1995 |
---|---|
Principal Product | Icemakers, circuit boards, and bomb fuse cables |
NAICS |
n/a
|
SIC | 3469: Metal Stampings, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 725 |
Plant Area |
162,000
ft2
|
Annual Production | 500,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $294,846 | 4,871,337 |
kWh
|
$0.061 |
Natural Gas | $11,883 | 2,132 |
MMBtu
|
$5.57 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $49,461 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,371 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Other Liquid (haz) Savings | Gaseous Waste Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $7,423 | $5,320 |
$4,836
109,906
kWh
|
$2,587
-
MMBtu
|
- | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $1,157 | $900 |
$1,157
21,102
kWh
|
- | - | - | - | |
03 | 2.4314: Use synthetic lubricant | $1,030 | - |
$1,030
18,757
kWh
|
- | - | - | - | |
04 | 2.2511: Insulate bare equipment | $761 | $788 |
$761
17,292
kWh
|
- | - | - | - | |
05 | 2.6211: Conserve energy by efficient use of vending machines | $567 | $1,275 |
$567
12,896
kWh
|
- | - | - | - | |
06 | 3.1191: Change procedures / equipment / operating conditions | $27,755 | $24,000 | - | - |
$19,380
-
gal
|
$8,375
-
lb
|
- | |
07 | 3.8143: Recycle cleaning solvent and reuse | $10,768 | $12,400 | - | - |
$6,089
-
gal
|
- | $4,679 | |
TOTAL RECOMMENDED | $49,461 | $44,683 |
$8,351
179,953
kWh
|
$2,587
-
MMBtu
|
$25,469
-
gal
|
$8,375
-
lb
|
$4,679 | ||
TOTAL IMPLEMENTED | $10,371 | $7,008 |
$7,784
167,057
kWh
|
$2,587
-
MMBtu
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Other Liquid (haz) Savings | Gaseous Waste Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs