| Assessment Year | 1994 |
|---|---|
| Principal Product | Color printed brochures, catalogs and calendars |
| NAICS |
n/a
|
| SIC | 2731: Books: Publishing, or Publishing and Printing |
| Sales Range | $5 M to 10M |
| # of Employees | 75 |
| Plant Area |
37,000
ft2
|
| Annual Production | 30,000,000
pieces
|
| Production Hrs. Annual | 7,488
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $71,520 | 1,521,395 |
kWh
|
$0.047 |
| Natural Gas | $12,515 | 1,875 |
MMBtu
|
$6.67 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $100,360 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,281 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,495 | $9,920 |
$3,495
65,944
kWh
|
- | |
| 02 | 2.7261: Install timers and/or thermostats | $2,466 | $1,200 |
$2,466
52,462
kWh
|
- | |
| 03 | 2.7111: Reduce illumination to minimum necessary levels | $1,161 | - |
$1,161
24,619
kWh
|
- | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $854 | - |
$854
18,171
kWh
|
- | |
| 05 | 2.2625: Chill water to the highest temperature possible | $537 | - |
$537
11,430
kWh
|
- | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $482 | $367 |
$482
10,258
kWh
|
- | |
| 07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $427 | $860 |
$427
9,086
kWh
|
- | |
| 08 | 2.4221: Install compressor air intakes in coolest locations | $262 | $240 |
$262
5,569
kWh
|
- | |
| 09 | 2.2511: Insulate bare equipment | $179 | $220 |
$179
3,810
kWh
|
- | |
| 10 | 3.1192: Reduce scrap production | $45,069 | $91,600 | - |
$45,069
-
lb
|
|
| 11 | 3.1162: Use less wasteful packaging | $21,100 | $34,000 | - |
$21,100
-
lb
|
|
| 12 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $19,372 | $10,640 | - |
$19,372
-
lb
|
|
| 13 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $4,956 | $13,600 | - |
$4,956
-
lb
|
|
| TOTAL RECOMMENDED | $100,360 | $162,647 |
$9,863
201,349
kWh
|
$90,497
-
lb
|
||
| TOTAL IMPLEMENTED | $6,281 | $11,367 |
$6,281
125,147
kWh
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs