Assessment Year | 1994 |
---|---|
Principal Product | Urethane foam cushions |
NAICS |
n/a
|
SIC | 3086: Plastics Foam Products |
Sales Range | $10 M to 50M |
# of Employees | 104 |
Plant Area |
163,000
ft2
|
Annual Production | 1,300
ton
|
Production Hrs. Annual | 6,864
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $123,125 | 2,619,578 |
kWh
|
$0.047 |
Natural Gas | $114,920 | 17,376 |
MMBtu
|
$6.61 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $34,971 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,665 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $7,494 | $1,620 |
$1,198
25,498
kWh
|
$6,296
-
MMBtu
|
|
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,681 | $4,140 |
$1,681
35,756
kWh
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $1,198 | $520 |
$1,198
25,498
kWh
|
- | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,185 | $870 |
$1,185
24,033
kWh
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $909 | $221 |
$909
19,343
kWh
|
- | |
06 | 2.4314: Use synthetic lubricant | $906 | - |
$906
19,343
kWh
|
- | |
07 | 2.2511: Insulate bare equipment | $376 | $65 | - |
$376
-
MMBtu
|
|
08 | 2.1223: Install smaller boiler (increase high fire duty cycle) | $21,222 | $16,000 |
$52,910
1,117,819
kWh
|
$(-31,688.0)
-
MMBtu
|
|
TOTAL RECOMMENDED | $34,971 | $23,436 |
$59,987
1,267,290
kWh
|
$(-25,016.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $3,665 | $1,455 |
$3,289
68,874
kWh
|
$376
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs