| Assessment Year | 2018 |
|---|---|
| Principal Product | Powertrain components |
| NAICS | 336350: Motor Vehicle Transmission and Power Train Parts Manufacturing |
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $50 M to 100M |
| # of Employees | 189 |
| Plant Area |
169,970
ft2
|
| Annual Production | 6,120,000
pieces
|
| Production Hrs. Annual | 6,912
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $1,440,109 | 22,610,232 |
kWh
|
$0.064 | |
| Natural Gas | $629,107 | 172,588 |
MMBtu
|
$3.65 | |
| Waste Disposal Costs | |||||
| Water Usage | $37,541 | 9,191 |
Tgal
|
$4.08 | |
| Water Disposal | $37,541 | 9,191 |
Tgal
|
$4.08 | |
| TOTAL YEARLY COSTS | $2,144,297 | ||||
| RECOMMENDED SAVINGS* | $130,898 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $51,173 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2515: Use optimum thickness insulation | $2,053 | $50 | - |
$2,053
-
MMBtu
|
|
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $24,981 | $14,930 |
$24,981
390,328
kWh
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,566 | $1,500 |
$6,566
102,594
kWh
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $852 | $750 |
$852
13,313
kWh
|
- | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $13,616 | $10,000 |
$13,616
212,750
kWh
|
- | |
| 06 | 2.4239: Eliminate or reduce compressed air usage | $1,684 | - |
$1,684
26,309
kWh
|
- | |
| 07 | 2.7231: Use radiant heater for spot heating | $42,420 | $47,500 | - |
$42,420
-
MMBtu
|
|
| 08 | 2.4131: Size electric motors for peak operating efficiency | $22,981 | $69,925 |
$22,981
359,077
kWh
|
- | |
| 09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,474 | $11,000 |
$3,474
54,287
kWh
|
- | |
| 10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $12,271 | $21,975 |
$12,271
191,738
kWh
|
- | |
| TOTAL RECOMMENDED | $130,898 | $177,630 |
$86,425
1,350,396
kWh
|
$44,473
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $51,173 | $38,180 |
$51,173
799,581
kWh
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs