Assessment Year | 1993 |
---|---|
Principal Product | Railcar bearing assemblies |
NAICS |
n/a
|
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
40,000
ft2
|
Annual Production | 320
ton
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $103,386 | 2,079,426 |
kWh
|
$0.050 |
Natural Gas | $47,808 | 8,408 |
MMBtu
|
$5.69 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $8,330 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,436 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
---|---|---|---|---|---|
01 | 2.7144: Install spectral reflectors / delamp | $4,608 | $5,042 |
$4,608
84,994
kWh
|
|
02 | 2.7261: Install timers and/or thermostats | $1,890 | $1,460 |
$1,890
37,808
kWh
|
|
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $645 | - |
$645
12,896
kWh
|
|
04 | 2.4314: Use synthetic lubricant | $513 | - |
$513
10,258
kWh
|
|
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $366 | $242 |
$366
7,327
kWh
|
|
06 | 2.4221: Install compressor air intakes in coolest locations | $249 | $440 |
$249
4,982
kWh
|
|
07 | 2.6212: Turn off equipment during breaks, reduce operating time | $59 | $560 |
$59
1,172
kWh
|
|
TOTAL RECOMMENDED | $8,330 | $7,744 |
$8,330
159,437
kWh
|
||
TOTAL IMPLEMENTED | $7,436 | $7,304 |
$7,436
141,559
kWh
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs