ITAC Assessment: TN0500
ITAC logo
ITAC Assessment: TN0500
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Railcar bearing assemblies
NAICS
n/a
SIC 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 40,000
ft2
Annual Production 320
ton
Production Hrs. Annual 6,240
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $103,386 2,079,426
kWh
Natural Gas $47,808 8,408
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,330 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,436

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7144: Install spectral reflectors / delamp $4,608 $5,042 $4,608
84,994
kWh
02 2.7261: Install timers and/or thermostats $1,890 $1,460 $1,890
37,808
kWh
03 2.4231: Reduce the pressure of compressed air to the minimum required $645 - $645
12,896
kWh
04 2.4314: Use synthetic lubricant $513 - $513
10,258
kWh
05 2.7142: Utilize higher efficiency lamps and/or ballasts $366 $242 $366
7,327
kWh
06 2.4221: Install compressor air intakes in coolest locations $249 $440 $249
4,982
kWh
07 2.6212: Turn off equipment during breaks, reduce operating time $59 $560 $59
1,172
kWh
TOTAL RECOMMENDED $8,330 $7,744 $8,330
159,437
kWh
TOTAL IMPLEMENTED $7,436 $7,304 $7,436
141,559
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs