| Assessment Year | 1992 |
|---|---|
| Principal Product | PLASTIC PARTS |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 420 |
| Plant Area |
n/a
|
| Annual Production | 11,000,000
lb
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $897,366 | 18,084,701 |
kWh
|
$0.050 |
| Natural Gas | $47,554 | 7,672 |
MMBtu
|
$6.20 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $109,121 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $77,374 | $825 |
$77,374
1,547,480
kWh
|
- | - | |
| 02 | 2.7261: Install timers and/or thermostats | $766 | $3,150 |
$766
15,240
kWh
|
- | - | |
| 03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $3,509 | $2,980 | - |
$3,509
-
MMBtu
|
- | |
| 04 | 2.2511: Insulate bare equipment | $6,052 | $9,972 |
$6,052
121,043
kWh
|
- | - | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,554 | $3,200 |
$5,554
111,079
kWh
|
- | - | |
| 06 | 2.7111: Reduce illumination to minimum necessary levels | $8,546 | $120 |
$5,246
104,924
kWh
|
- | $3,300 | |
| 07 | 2.2511: Insulate bare equipment | $5,232 | $903 |
$5,232
104,631
kWh
|
- | - | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,088 | $608 |
$2,696
53,927
kWh
|
- | $(-608.0) | |
| TOTAL RECOMMENDED | $109,121 | $21,758 |
$102,920
2,058,324
kWh
|
$3,509
-
MMBtu
|
$2,692 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs