| Assessment Year | 1991 |
|---|---|
| Principal Product | BLANKETS, BEDSPREADS |
| NAICS |
n/a
|
| SIC | 2392: House furnishing, Except Curtains and Draperies |
| Sales Range | $50 M to 100M |
| # of Employees | 650 |
| Plant Area |
n/a
|
| Annual Production | 12,120,000
pieces
|
| Production Hrs. Annual | 8,232
hrs
|
| Location (State) | South Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,029,949 | 22,050,118 |
kWh
|
$0.047 |
| Natural Gas | $225,315 | 49,675 |
MMBtu
|
$4.54 |
| Coal | $200,751 | 143,220 |
MMBtu
|
$1.40 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $56,284 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Coal Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2136: Install / repair insulation on steam lines | $5,308 | $2,090 | - |
$5,308
-
MMBtu
|
- | |
| 02 | 2.2135: Repair and eliminate steam leaks | $1,631 | $770 | - |
$1,631
-
MMBtu
|
- | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $13,017 | - |
$13,017
276,964
kWh
|
- | - | |
| 04 | 2.2511: Insulate bare equipment | $1,295 | $2,396 | - |
$1,295
-
MMBtu
|
- | |
| 05 | 2.2135: Repair and eliminate steam leaks | $1,013 | $100 | - |
$1,013
-
MMBtu
|
- | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $5,813 | $1,440 |
$5,813
123,681
kWh
|
- | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,746 | - |
$8,430
179,367
kWh
|
- | $(-1,684.0) | |
| 08 | 2.6232: Install set-back timers | $1,708 | - |
$1,708
36,342
kWh
|
- | - | |
| 09 | 2.3191: Use demand controller or load shedder | $19,753 | $20,800 |
$19,753
-
kWh
|
- | - | |
| TOTAL RECOMMENDED | $56,284 | $27,596 |
$48,721
616,354
kWh
|
$9,247
-
MMBtu
|
$(-1,684.0) | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Coal Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs