| Assessment Year | 1991 |
|---|---|
| Principal Product | METAL STAMPING |
| NAICS |
n/a
|
| SIC | 3496: Miscellaneous Fabricated Wire Products |
| Sales Range | $5 M to 10M |
| # of Employees | 90 |
| Plant Area |
n/a
|
| Annual Production | 50,000,000
pieces
|
| Production Hrs. Annual | 4,394
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $44,687 | 699,883 |
kWh
|
$0.064 |
| LPG | $30,641 | 3,252 |
MMBtu
|
$9.42 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $18,457 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $18,457 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,971 | $6,000 |
$4,971
77,667
kWh
|
- | - | |
| 02 | 2.6212: Turn off equipment during breaks, reduce operating time | $2,926 | - |
$2,926
45,721
kWh
|
- | - | |
| 03 | 2.7123: Keep lamps and reflectors clean | $2,939 | $4,256 |
$2,757
43,083
kWh
|
- | $182 | |
| 04 | 2.6232: Install set-back timers | $1,932 | - |
$1,932
30,188
kWh
|
- | - | |
| 05 | 2.7226: Use computer programs to optimize hvac performance | $892 | $190 | - |
$892
-
MMBtu
|
- | |
| 06 | 2.2514: Cover open tanks | $910 | $315 |
$225
3,517
kWh
|
$685
-
MMBtu
|
- | |
| 07 | 2.7447: Install vinyl strip / high speed / air curtain doors | $244 | $410 | - |
$244
-
MMBtu
|
- | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $338 | $322 |
$338
5,275
kWh
|
- | - | |
| 09 | 2.3191: Use demand controller or load shedder | $3,305 | $9,700 |
$3,305
-
kWh
|
- | - | |
| TOTAL RECOMMENDED | $18,457 | $21,193 |
$16,454
205,451
kWh
|
$1,821
-
MMBtu
|
$182 | ||
| TOTAL IMPLEMENTED | $18,457 | $21,193 |
$16,454
205,451
kWh
|
$1,821
-
MMBtu
|
$182 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | LPG Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs