ITAC Assessment: TN0421
ITAC logo
ITAC Assessment: TN0421
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product ALUMINUM OIL COOLERS
NAICS
n/a
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area
n/a
Annual Production 48,000
pieces
Production Hrs. Annual 4,250
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $197,464 3,844,666
kWh
Natural Gas $95,817 30,731
MMBtu
LPG $24,120 3,298
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $46,485 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $46,485

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings LPG Savings Administrative Changes Savings
01 2.2531: Re-size charging openings or add movable cover or door $30,358 $17,288 $30,358
595,252
kWh
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $9,865 $390 $9,865
193,435
kWh
- - -
03 2.2153: Close off unneeded steam lines $1,536 - - $1,189
-
MMBtu
$347
-
MMBtu
-
04 2.2514: Cover open tanks $944 $500 - $731
-
MMBtu
$213
-
MMBtu
-
05 2.2163: Use minimum steam operating pressure $417 - - $322
-
MMBtu
$95
-
MMBtu
-
06 2.7123: Keep lamps and reflectors clean $1,855 $5,475 $1,555
30,481
kWh
- - $300
07 2.6232: Install set-back timers $613 - $613
12,016
kWh
- - -
08 2.4221: Install compressor air intakes in coolest locations $553 $490 $553
10,844
kWh
- - -
09 2.6218: Turn off equipment when not in use $344 $470 $344
6,741
kWh
- - -
TOTAL RECOMMENDED $46,485 $24,613 $43,288
848,769
kWh
$2,242
-
MMBtu
$655
-
MMBtu
$300
TOTAL IMPLEMENTED $46,485 $24,613 $43,288
848,769
kWh
$2,242
-
MMBtu
$655
-
MMBtu
$300
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings LPG Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs