Assessment Year | 1990 |
---|---|
Principal Product | TOOTH & SCRUB BRUSHES |
NAICS |
n/a
|
SIC | 3991: Brooms and Brushes |
Sales Range | $10 M to 50M |
# of Employees | 375 |
Plant Area |
n/a
|
Annual Production | 140,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $506,118 | 9,667,937 |
kWh
|
$0.052 |
Natural Gas | $15,953 | 2,483 |
MMBtu
|
$6.42 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $98,316 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $72,539 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7123: Keep lamps and reflectors clean | $25,287 | $29,907 |
$22,647
435,522
kWh
|
- | $2,640 | |
02 | 2.6232: Install set-back timers | $11,948 | - |
$11,948
229,777
kWh
|
- | - | |
03 | 2.3212: Optimize plant power factor | $13,343 | $44,500 |
$13,343
-
kWh
|
- | - | |
04 | 2.7261: Install timers and/or thermostats | $11,650 | $7,440 |
$8,245
158,558
kWh
|
$3,405
-
MMBtu
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $14,844 | $930 |
$14,844
285,463
kWh
|
- | - | |
06 | 2.6232: Install set-back timers | $9,891 | $7,200 |
$9,891
190,211
kWh
|
- | - | |
07 | 2.4312: Improve lubrication practices | $3,261 | - |
$3,261
62,720
kWh
|
- | - | |
08 | 2.6122: Adjust vents to minimize energy use | $2,515 | $3,600 |
$2,515
48,359
kWh
|
- | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,602 | - |
$5,440
104,631
kWh
|
- | $(-838.0) | |
10 | 2.6122: Adjust vents to minimize energy use | $975 | $1,545 |
$975
18,757
kWh
|
- | - | |
TOTAL RECOMMENDED | $98,316 | $95,122 |
$93,109
1,533,998
kWh
|
$3,405
-
MMBtu
|
$1,802 | ||
TOTAL IMPLEMENTED | $72,539 | $78,937 |
$70,737
1,103,752
kWh
|
- | $1,802 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs