Assessment Year | 1988 |
---|---|
Principal Product | STRAPS, HUBS & SPINDLES |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 160 |
Plant Area |
n/a
|
Annual Production | 7,200,000
lb
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $332,033 | 6,495,897 |
kWh
|
$0.051 |
Natural Gas | $32,364 | 6,071 |
MMBtu
|
$5.33 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $36,474 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $28,058 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,000 | $900 |
$11,000
215,709
kWh
|
- | |
02 | 2.7141: Lower light fixtures in high ceiling areas | $7,743 | $4,388 |
$7,743
151,817
kWh
|
- | |
03 | 2.2437: Recover waste heat from equipment | $4,409 | $1,380 | - |
$4,409
-
MMBtu
|
|
04 | 2.2511: Insulate bare equipment | $3,004 | $355 |
$3,004
58,910
kWh
|
- | |
05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $928 | $1,110 | - |
$928
-
MMBtu
|
|
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,541 | - |
$2,541
49,824
kWh
|
- | |
07 | 2.7261: Install timers and/or thermostats | $1,315 | $560 |
$1,315
25,791
kWh
|
- | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $673 | $180 |
$673
13,189
kWh
|
- | |
09 | 2.7122: Disconnect ballasts | $254 | $273 |
$254
4,982
kWh
|
- | |
10 | 2.3212: Optimize plant power factor | $4,607 | $6,600 |
$4,607
-
kWh
|
- | |
TOTAL RECOMMENDED | $36,474 | $15,746 |
$31,137
520,222
kWh
|
$5,337
-
MMBtu
|
||
TOTAL IMPLEMENTED | $28,058 | $11,178 |
$22,721
355,216
kWh
|
$5,337
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs